Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address NEW:
5204 S CHAMPION SV
Apply Date:
12/17/2025
Applicant:
Cynthia Smith
Description:
We are working with the COT-Grow Tucson to install Rainwater Harvesting Basins, Boulders, and Berms in the ROW area N of 5204 S Champion SV.

Permit Reviews

Permit Number - TR-ROW-1225-01541
Permit Status: Complete
Permit Description: We are working with the COT-Grow Tucson to install Rainwater Harvesting Basins, Boulders, and Berms in the ROW area N of 5204 S Champion SV.
Start Date Submittal Complete Date Status  
12/17/2025 RIGHT-OF-WAY REVIEW v.1 01/07/2026 REQUIRES RESUBMIT Review Details
01/08/2026 RIGHT-OF-WAY REVIEW v.2 01/09/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-1225-01541
Permit Status: Complete
Permit Description: We are working with the COT-Grow Tucson to install Rainwater Harvesting Basins, Boulders, and Berms in the ROW area N of 5204 S Champion SV.
Total Outstanding Activity Conditions - 2
Date Name
12/17/2025 ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14
12/17/2025 Traffic control set-up approved between 9AM - 3:30PM

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-1225-01541
Permit Description: We are working with the COT-Grow Tucson to install Rainwater Harvesting Basins, Boulders, and Berms in the ROW area N of 5204 S Champion SV.
Total Completed Inspections - 4
Date Description Inspector Results Comments
02/13/2026 TRSP - ROW - Barricade - Setup/Routine Passed Work is complete
02/13/2026 TRSP - ROW - Backfill - Placement/Compaction Passed Work is already complete
02/13/2026 TRSP - ROW - Final Passed Work is complete
02/13/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed Site is ready for work to begin

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
100__COT GT_6TH TRIANGLE-11.11.25(2)_V1.PDF DOCUMENTS VIEW
ECO CHAMPION_V1.PDF DOCUMENTS VIEW
ECO TCP CHAMPION_V1(1)_V2.PDF DOCUMENTS VIEW