Permit: TR-ROW-1224-01452
Permit Details
Apply Date:
12/20/2024
Applicant:
Miguel Gonzalez
Description:
** CONTINUATION OF TR-ROW-0524-00615** Maintenance project: Fiber pull thru existing conduits, placing 2 new handholes, to be placed next to existing handholes (south on Park Ave from Bantam Rd to Mossman Rd) 2 Handholes to be placed in dirt, 1 handhole to be placed in concrete
Permit Reviews
Permit Number - TR-ROW-1224-01452
Permit Status: Complete
Permit Description: ** CONTINUATION OF TR-ROW-0524-00615** Maintenance project: Fiber pull thru existing conduits, placing 2 new handholes, to be placed next to existing handholes (south on Park Ave from Bantam Rd to Mossman Rd)
2 Handholes to be placed in dirt, 1 handhole to be placed in concrete
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/23/2024 | RIGHT-OF-WAY REVIEW v.1 | 12/27/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-1224-01452
Permit Status: Complete
Permit Description: ** CONTINUATION OF TR-ROW-0524-00615** Maintenance project: Fiber pull thru existing conduits, placing 2 new handholes, to be placed next to existing handholes (south on Park Ave from Bantam Rd to Mossman Rd)
2 Handholes to be placed in dirt, 1 handhole to be placed in concrete
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 12/26/2024 | Traffic control set-up approved between 9AM - 3:30PM |
| 12/26/2024 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-1224-01452
Permit Description: ** CONTINUATION OF TR-ROW-0524-00615** Maintenance project: Fiber pull thru existing conduits, placing 2 new handholes, to be placed next to existing handholes (south on Park Ave from Bantam Rd to Mossman Rd)
2 Handholes to be placed in dirt, 1 handhole to be placed in concrete
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/26/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 04/16/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 04/16/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 04/16/2025 | TRSP - ROW - Final | Passed |