Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Apply Date:
11/11/2022
Applicant:
Amy Stokes, Operations Accountant
Description:
homesite driveway/sidewalk

Permit Reviews

Permit Number - TR-ROW-1122-00064
Permit Status: Complete
Permit Description: homesite driveway/sidewalk
Start Date Submittal Complete Date Status  
12/05/2022 RIGHT-OF-WAY REVIEW v.1 12/06/2022 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-1122-00064
Permit Status: Complete
Permit Description: homesite driveway/sidewalk
Total Outstanding Activity Conditions - 2
Date Name
06/15/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
06/15/2023 Sewer condition must be accepted and released by Pima County

Conditions

Permit Number - TR-ROW-1122-00064
Permit Status: Complete
Permit Description: homesite driveway/sidewalk
Date Description Comments
12/06/2022 The following extended traffic control set-up times were approved:

Outstanding Inspections

Permit Status: Complete
Permit Number: TR-ROW-1122-00064
Permite Description: homesite driveway/sidewalk
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
01/27/2023 TRSP - ROW - Recurring N/A Re-inspection required Inspected forms everything good ready to pour.

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-1122-00064
Permit Description: homesite driveway/sidewalk
Total Completed Inspections - 2
Date Description Inspector Results Comments
09/09/2024 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed Jeremy and contractor completed pre con meeting
09/09/2024 TRSP - ROW - Final/Close-Out Passed Zac Staten verified and approved final site