Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
In Review
Type:
Right-of-Way (ROW)
Address:
201 N STONE AV
Address NEW:
201 N STONE AV
Apply Date:
10/16/2026
Applicant:
juan moreno
Description:
Install 144SM fiber from 201 N. Stone to 150 W Congress. Cable will be installed in an existing conduit path. Pull boxes are adjacent to the sidewalk

Permit Reviews

Permit Number - TR-ROW-1026-01149
Permit Status: In review
Permit Description: Install 144SM fiber from 201 N. Stone to 150 W Congress. Cable will be installed in an existing conduit path. Pull boxes are adjacent to the sidewalk
Start Date Submittal Complete Date Status  
11/23/2026 RIGHT-OF-WAY REVIEW v.3 N/A IN REVIEW Review Details
10/21/2026 RIGHT-OF-WAY REVIEW v.1 10/23/2026 REQUIRES RESUBMIT Review Details
11/04/2026 RIGHT-OF-WAY REVIEW v.2 11/20/2026 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-1026-01149
Permit Status: In review
Permit Description: Install 144SM fiber from 201 N. Stone to 150 W Congress. Cable will be installed in an existing conduit path. Pull boxes are adjacent to the sidewalk
Total Outstanding Activity Conditions - 6
Date Name
10/21/2026 This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to the Historic Preservation Office, City of Tucson, PO BOX 27210, Tucson AZ 85726...***Please contact Historic Preservation Office at PDSDHistoric@tucsonaz.gov.
10/21/2026 BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION.
10/21/2026 Traffic control set-up approved between 9AM - 3:30PM
10/21/2026 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
10/21/2026 Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online.
11/09/2026 A NOTICE OF TEMPORARY HOLIDAY RESTRICTION applies to this permit and will be effect from NOV 23rd to January 3rd. Due to increase traffic volume on many of the city roads, its necessary to restrict lane closures on certain roads during the Gem Show.