Permit: TR-ROW-1026-01141
Permit Details
Apply Date:
10/15/2026
Applicant:
Description:
We will need to close the bus bay and relocate the bus stop on Northbound Stone Ave. North of Speedway Blvd. We will be trouble Shooting an AT&T small cell site. Will be using a bucket truck to access the Pole. RCB*-*
Permit Reviews
Permit Number - TR-ROW-1026-01141
Permit Status: Fees due
Permit Description: We will need to close the bus bay and relocate the bus stop on Northbound Stone Ave. North of Speedway Blvd. We will be trouble Shooting an AT&T small cell site. Will be using a bucket truck to access the Pole.
RCB*-*
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/16/2026 | RIGHT-OF-WAY REVIEW v.2 | 11/19/2026 | APPROVED |
| 10/19/2026 | RIGHT-OF-WAY REVIEW v.1 | 11/13/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-1026-01141
Permit Status: Fees due
Permit Description: We will need to close the bus bay and relocate the bus stop on Northbound Stone Ave. North of Speedway Blvd. We will be trouble Shooting an AT&T small cell site. Will be using a bucket truck to access the Pole.
RCB*-*
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 10/21/2026 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
| 10/21/2026 | Historic Preservation Office at PDSDHistoric@tucsonaz.gov. |
| 10/21/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 10/21/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 10/21/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 11/19/2026 | Continuous ADA-compliant pedestrian access shall be maintained at all times. If a sidewalk is closed, an approved temporary pedestrian access route shall be provided in accordance with the Manual on Uniform Traffic Control Devices. |
| 11/19/2026 | Lane and street closures shall be permitted only during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four-hour lane closures are not permitted unless specifically approved by the City. Traffic control devices shall not be stored in a bike lane or sidewalk |