Permit: TR-ROW-1026-01122
Permit Details
Status:
In Review
Type:
Right-of-Way (ROW)
Address:
4239 E BELLEVUE ST
Address NEW:
4239 E BELLEVUE ST
Apply Date:
10/08/2026
Applicant:
Andres Amado
Description:
ROW permit for investigation and possible repair work to be done to Critical Tucson water 54in main. testing system has detected structural abnormalities at two locations. Tucson water needs up to excavate and investigate at both locations to ensure they are no failing. if found to be unsafe, external repairs are to be made at these locations. later to be reinforced internally. work to be completed prior to Thanksgiving weekend
Permit Reviews
Permit Number - TR-ROW-1026-01122
Permit Status: In review
Permit Description: ROW permit for investigation and possible repair work to be done to Critical Tucson water 54in main. testing system has detected structural abnormalities at two locations. Tucson water needs up to excavate and investigate at both locations to ensure they are no failing. if found to be unsafe, external repairs are to be made at these locations. later to be reinforced internally. work to be completed prior to Thanksgiving weekend
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/09/2026 | RIGHT-OF-WAY REVIEW v.1 | 11/10/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-1026-01122
Permit Status: In review
Permit Description: ROW permit for investigation and possible repair work to be done to Critical Tucson water 54in main. testing system has detected structural abnormalities at two locations. Tucson water needs up to excavate and investigate at both locations to ensure they are no failing. if found to be unsafe, external repairs are to be made at these locations. later to be reinforced internally. work to be completed prior to Thanksgiving weekend
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 10/12/2026 | The following extended traffic control set-up times were approved: 24 hrs |
| 10/12/2026 | Pre-Activity Meeting: |
| 11/10/2026 | Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9- |
Outstanding Inspections
Permit Status: In Review
Permit Number: TR-ROW-1026-01122
Permite Description: ROW permit for investigation and possible repair work to be done to Critical Tucson water 54in main. testing system has detected structural abnormalities at two locations. Tucson water needs up to excavate and investigate at both locations to ensure they are no failing. if found to be unsafe, external repairs are to be made at these locations. later to be reinforced internally. work to be completed prior to Thanksgiving weekend
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| Required: Start Work Notice - Notify your DTM Inspector of your work start date. Notification only; you will be contacted if a Pre-Activity Meeting is needed. | N/A | Scheduled |
Completed Inspections
Permit Status: In Review
Permit Number: TR-ROW-1026-01122
Permit Description: ROW permit for investigation and possible repair work to be done to Critical Tucson water 54in main. testing system has detected structural abnormalities at two locations. Tucson water needs up to excavate and investigate at both locations to ensure they are no failing. if found to be unsafe, external repairs are to be made at these locations. later to be reinforced internally. work to be completed prior to Thanksgiving weekend
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/12/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed |
Scheduled Inspections
Scheduled Inspections - TR-ROW-1026-01122
Status: In Review
Description: ROW permit for investigation and possible repair work to be done to Critical Tucson water 54in main. testing system has detected structural abnormalities at two locations. Tucson water needs up to excavate and investigate at both locations to ensure they are no failing. if found to be unsafe, external repairs are to be made at these locations. later to be reinforced internally. work to be completed prior to Thanksgiving weekend
| Scheduled Date | Description | Entered By | Entered Date |
|---|---|---|---|
| 11/16/2026 | Required: Start Work Notice - Notify your DTM Inspector of your work start date. Notification only; you will be contacted if a Pre-Activity Meeting is needed. | Scheduled |
For information about today’s scheduled inspections please refer to the
PDSD Daily Inspections Dashboards (Desktop)
PDSD Daily Inspections Dashboards (Mobile)
.