Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TR-ROW-1025-01312
Permit Details
Apply Date:
10/23/2025
Applicant:
Jonathan Sapan
Description:
Excavation of storm water harvesting basins in right of way along 3rd Ave.
Permit Reviews
Permit Number - TR-ROW-1025-01312
Permit Status: Complete
Permit Description: Excavation of storm water harvesting basins in right of way along 3rd Ave.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/27/2025 | RIGHT-OF-WAY REVIEW v.2 | 10/28/2025 | APPROVED |
| 10/24/2025 | RIGHT-OF-WAY REVIEW v.1 | 10/27/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-1025-01312
Permit Status: Complete
Permit Description: Excavation of storm water harvesting basins in right of way along 3rd Ave.
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 10/24/2025 | Traffic Control set-up approved between 7AM - 5PM |
| 10/24/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 10/24/2025 | SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. REPLACE/REPAIR SIDEWALKS PANELS PER PAG STANDARD DETAIL 200/206 |
| 10/28/2025 | Pre-Activity Meeting w/Inspections Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-1025-01312
Permit Description: Excavation of storm water harvesting basins in right of way along 3rd Ave.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/31/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 11/20/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 11/20/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 11/21/2025 | TRSP - ROW - Final | Passed |