Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address NEW:
3207 E WAVERLY ST
Apply Date:
10/22/2025
Applicant:
Description:
6 Water-harvesting basins and plantings in Public right-of-way adjoining street. 5 curb cores leaving minimum 2" clearance of solid core above core hole. Initial excavation will be done in 1-2 days, then shaping and rocking of edges will happen on the consecutive weekends following (11/8 & 11/15).

Permit Reviews

Permit Number - TR-ROW-1025-01300
Permit Status: Complete
Permit Description: 6 Water-harvesting basins and plantings in Public right-of-way adjoining street. 5 curb cores leaving minimum 2" clearance of solid core above core hole. Initial excavation will be done in 1-2 days, then shaping and rocking of edges will happen on the consecutive weekends following (11/8 & 11/15).
Start Date Submittal Complete Date Status  
10/28/2025 RIGHT-OF-WAY REVIEW v.2 10/30/2025 APPROVED Review Details
10/22/2025 RIGHT-OF-WAY REVIEW v.1 10/24/2025 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-1025-01300
Permit Status: Complete
Permit Description: 6 Water-harvesting basins and plantings in Public right-of-way adjoining street. 5 curb cores leaving minimum 2" clearance of solid core above core hole. Initial excavation will be done in 1-2 days, then shaping and rocking of edges will happen on the consecutive weekends following (11/8 & 11/15).
Total Outstanding Activity Conditions - 2
Date Name
10/23/2025 PRE-CON/ PAVEMENT/ SIDEWALKS
10/23/2025 Traffic Control set-up approved between 7AM - 5PM

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-1025-01300
Permit Description: 6 Water-harvesting basins and plantings in Public right-of-way adjoining street. 5 curb cores leaving minimum 2" clearance of solid core above core hole. Initial excavation will be done in 1-2 days, then shaping and rocking of edges will happen on the consecutive weekends following (11/8 & 11/15).
Total Completed Inspections - 4
Date Description Inspector Results Comments
11/26/2025 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
12/03/2025 TRSP - ROW - Barricade - Setup/Routine Passed
12/03/2025 TRSP - ROW - Backfill - Placement/Compaction Passed
12/03/2025 TRSP - ROW - Final Passed

Documents

File Name Document Type  
10-21-2025_V1.PDF DOCUMENTS VIEW
COMBINE OCTOBER 28, 2025_V1.PDF DOCUMENTS VIEW
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW