Apply Date:
10/31/2024
Applicant:
Erica Goldston
Description:
Sewer line rehab (CIPP Lining), MH Bench Rehabs, MH Collars, Point Repairs, New MH Installs. This is associated with the Prop 101 Rehab Package 5 Project.
Permit Reviews
Permit Number - TR-ROW-1024-01278
Permit Status: Complete
Permit Description: Sewer line rehab (CIPP Lining), MH Bench Rehabs, MH Collars, Point Repairs, New MH Installs. This is associated with the Prop 101 Rehab Package 5 Project.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/31/2024 | RIGHT-OF-WAY REVIEW v.1 | 11/06/2024 | REQUIRES RESUBMIT |
| 11/07/2024 | RIGHT-OF-WAY REVIEW v.2 | 11/14/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-1024-01278
Permit Status: Complete
Permit Description: Sewer line rehab (CIPP Lining), MH Bench Rehabs, MH Collars, Point Repairs, New MH Installs. This is associated with the Prop 101 Rehab Package 5 Project.
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 11/01/2024 | BUS STOP/ROUTE |
| 11/01/2024 | PRE-CON/PAVEMENT/SIDEWALK |
| 11/01/2024 | Traffic control set-up approved between 9AM - 3:30PM |
| 11/07/2024 | The following extended traffic control set-up times were approved: |
| 11/07/2024 | Temporary Noise Exemption |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-1024-01278
Permit Description: Sewer line rehab (CIPP Lining), MH Bench Rehabs, MH Collars, Point Repairs, New MH Installs. This is associated with the Prop 101 Rehab Package 5 Project.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/18/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 01/17/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 01/17/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 01/17/2025 | TRSP - ROW - Final | Passed |