Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address:
8652 E STELLA RD
Address NEW:
8652 E STELLA RD
Apply Date:
09/18/2025
Applicant:
Armando Bracamonte
Description:
The contractor will be installing speed solar radar signs for Abel Rosales for the City of Tucson. Will be working on the shoulder.

Permit Reviews

Permit Number - TR-ROW-0925-01147
Permit Status: Complete
Permit Description: The contractor will be installing speed solar radar signs for Abel Rosales for the City of Tucson. Will be working on the shoulder.
Start Date Submittal Complete Date Status  
09/19/2025 RIGHT-OF-WAY REVIEW v.1 09/22/2025 REQUIRES RESUBMIT Review Details
09/23/2025 RIGHT-OF-WAY REVIEW v.2 09/23/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0925-01147
Permit Status: Complete
Permit Description: The contractor will be installing speed solar radar signs for Abel Rosales for the City of Tucson. Will be working on the shoulder.
Total Outstanding Activity Conditions - 1
Date Name
09/22/2025 Traffic control set-up approved between 9AM - 3:30PM

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0925-01147
Permit Description: The contractor will be installing speed solar radar signs for Abel Rosales for the City of Tucson. Will be working on the shoulder.
Total Completed Inspections - 4
Date Description Inspector Results Comments
09/25/2025 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed I spoke with Chris from Nextgen over the phone and he informed me that a start date would be Tuesday 09/30/25.
12/16/2025 TRSP - ROW - Barricade - Setup/Routine Passed Traffic control setup followed an approved TCP
12/16/2025 TRSP - ROW - Barricade Takedown Passed Work is complete
12/16/2025 TRSP - ROW - Final Passed Work is complete