Permit: TR-ROW-0925-01129
Permit Details
Apply Date:
09/15/2025
Applicant:
German Arvizu
Description:
Sidewalk repair
Permit Reviews
Permit Number - TR-ROW-0925-01129
Permit Status: Inspections
Permit Description: Sidewalk repair
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/15/2025 | RIGHT-OF-WAY REVIEW v.1 | 09/15/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0925-01129
Permit Status: Inspections
Permit Description: Sidewalk repair
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 09/15/2025 | UNDER A PAVEMENT MORATORIUM, ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES. |
| 09/15/2025 | Traffic Control set-up approved between 7AM - 5PM |
| 09/15/2025 | SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. REPLACE/REPAIR SIDEWALKS PANELS PER PAG STANDARD DETAIL 200/206 |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TR-ROW-0925-01129
Permite Description: Sidewalk repair
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/21/2025 | TRSP - ROW - Final | N/A | Re-inspection required | The site is not ready for concrete. The subgrade has not been leveled or compacted. The forms are not complete. There is no expansion material, and the stakes are not capped for safety. |
| 10/21/2025 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | N/A | Re-inspection required | The site is not ready for concrete. The subgrade has not been leveled or compacted. The forms are not complete. There is no expansion material, and the stakes are not capped for safety. |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-ROW-0925-01129
Permit Description: Sidewalk repair
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/17/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | I had a preconstruction meeting over the phone with Anthony from RVZ construction | |
| 10/27/2025 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed | Work is now complete, sidewalk has been repaired. Still waiting for the traffic control to be removed | |
| 10/27/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | Concrete has been poured and sidewalk is now repaired. The sidewalk closed barricades need to be removed |