Permit: TR-ROW-0925-01115
Permit Details
Apply Date:
09/11/2025
Applicant:
Andrew Ruiz
Description:
Convert overhead electrical to underground on Columbus Blvd and Tappen Dr, total excavation 90’ **24hrs**
Permit Reviews
Permit Number - TR-ROW-0925-01115
Permit Status: Complete
Permit Description: Convert overhead electrical to underground on Columbus Blvd and Tappen Dr, total excavation 90’
**24hrs**
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/29/2025 | RIGHT-OF-WAY REVIEW v.2 | 10/01/2025 | APPROVED |
| 09/12/2025 | RIGHT-OF-WAY REVIEW v.1 | 09/16/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0925-01115
Permit Status: Complete
Permit Description: Convert overhead electrical to underground on Columbus Blvd and Tappen Dr, total excavation 90’
**24hrs**
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 09/16/2025 | PRE-CON/PAVEMENT/SIDEWALK |
| 09/16/2025 | Traffic Control set-up approved between 7AM - 5PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0925-01115
Permit Description: Convert overhead electrical to underground on Columbus Blvd and Tappen Dr, total excavation 90’
**24hrs**
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/13/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 11/12/2025 | TRSP - ROW - AERIAL INSTALLATION | Passed | No aerial work for this permit | |
| 11/12/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | Work is complete | |
| 11/12/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | Already passed by Tristan | |
| 11/12/2025 | TRSP - ROW - Bituminous Treatment | Passed | Work is complete | |
| 11/12/2025 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | Passed | Work is complete | |
| 11/12/2025 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed | Work is complete | |
| 11/12/2025 | TRSP - ROW - Drainage - Pipe Installation/Removal | Passed | Work is complete but no drainage inspection was requested | |
| 11/12/2025 | TRSP - ROW - Field Change Request | Passed | This inspection was not needed | |
| 11/14/2025 | TRSP - ROW - Final | Passed | Work is complete | |
| 11/14/2025 | TRSP - ROW - Barricade Takedown | Passed | Work is complete |