Permit: TR-ROW-0826-00884
Permit Details
Status:
Inspections Complete
Type:
Right-of-Way (ROW)
Address:
1075 N GREASEWOOD RD
Address NEW:
1075 N GREASEWOOD RD
Apply Date:
08/10/2026
Applicant:
Desert Barricade / Eric Horne
Description:
Repair Damage Guardrail
Permit Reviews
Permit Number - TR-ROW-0826-00884
Permit Status: Inspections complete
Permit Description: Repair Damage Guardrail
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/12/2026 | RIGHT-OF-WAY REVIEW v.1 | 08/20/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0826-00884
Permit Status: Inspections complete
Permit Description: Repair Damage Guardrail
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 08/13/2026 | Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 08/13/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 08/13/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 08/20/2026 | Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign |
| 08/20/2026 | Lane closures shall only be permitted during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four (24) hour lane closures are not permitted unless specifically approved by the City. Traffic Control Devices shall not be stored in the bike lane or sidewalk |
| 08/20/2026 | No pedestrian detour is proposed; therefore, the sidewalk shall remain open and ADA-compliant at all times during construction. TC Company -assisted pedestrian access does not constitute a pedestrian detour and shall not require pedestrians to leave the designated pedestrian path. If the sidewalk cannot be maintained in an open and ADA-compliant condition, an approved pedestrian detour shall be implemented prior to any sidewalk closure. |
| 08/20/2026 | Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TR-ROW-0826-00884
Permit Description: Repair Damage Guardrail
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/28/2026 | Passed | No concrete just wooden post and guardrails repair Precon was discussed and script was read and understood for future reference. She has our card and contact information | ||
| 09/29/2026 | Required: Start Work Notice - Notify your DTM Inspector of your work start date. Notification only; you will be contacted if a Pre-Activity Meeting is needed. | Passed | work has been completed it stared on 9/01/2026 | |
| 09/29/2026 | TRSP - ROW - Notice of Completion | Passed | All the old gard rail has been replaced with new rail | |
| 09/29/2026 | Passed | All the old gard rail has been replaced with new rail | ||
| 10/21/2026 | Passed |