Permit: TR-ROW-0825-01075
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW)
Address:
4957 E FORT LOWELL RD
Address NEW:
4957 E FORT LOWELL RD
Apply Date:
08/29/2025
Applicant:
Caitlin Ripley - Southwest Barricades
Description:
Two 4'X4' Bore pits in dirt shoulder- Bore 65' under Ft. Lowell for Power tie in
Permit Reviews
Permit Number - TR-ROW-0825-01075
Permit Status: Complete
Permit Description: Two 4'X4' Bore pits in dirt shoulder- Bore 65' under Ft. Lowell for Power tie in
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/19/2025 | RIGHT-OF-WAY REVIEW v.3 | 09/19/2025 | APPROVED |
| 09/17/2025 | RIGHT-OF-WAY REVIEW v.2 | 09/18/2025 | REQUIRES RESUBMIT |
| 08/29/2025 | RIGHT-OF-WAY REVIEW v.1 | 09/03/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0825-01075
Permit Status: Complete
Permit Description: Two 4'X4' Bore pits in dirt shoulder- Bore 65' under Ft. Lowell for Power tie in
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 08/29/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 09/17/2025 | City of Tucson Right of Way Only ROW Permit is only allowed for work within City of Tucson Right of Way |
| 09/17/2025 | Pavement Condition and Restoration |
| 09/17/2025 | Pre-Activity Meeting |
| 09/17/2025 | Private Property |
| 09/17/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 09/19/2025 | Permit approval is Contingent on the the a Start Date AFTER November 8th, 2025 and will require the coordinate with the on-site inspector and ongoing CIP work |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0825-01075
Permit Description: Two 4'X4' Bore pits in dirt shoulder- Bore 65' under Ft. Lowell for Power tie in
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 12/10/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 05/04/2026 | TRSP - ROW - Barricade Takedown | Passed | ||
| 05/04/2026 | TRSP - ROW - Final | Passed |