Permit: TR-ROW-0825-01023
Permit Details
Apply Date:
08/18/2025
Applicant:
Description:
325003 Site 2 - Install approximately 343 LF of 8" Cured in Place Pipe from MH 8417-01 to MH 9907-166. Bench rehab, MH adjustment, and new frame and cover will be completed on MH 8417-01 and MH 9907-166.
Permit Reviews
Permit Number - TR-ROW-0825-01023
Permit Status: Complete
Permit Description: 325003 Site 2 - Install approximately 343 LF of 8" Cured in Place Pipe from MH 8417-01 to MH 9907-166. Bench rehab, MH adjustment, and new frame and cover will be completed on MH 8417-01 and MH 9907-166.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/18/2025 | RIGHT-OF-WAY REVIEW v.1 | 08/19/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0825-01023
Permit Status: Complete
Permit Description: 325003 Site 2 - Install approximately 343 LF of 8" Cured in Place Pipe from MH 8417-01 to MH 9907-166. Bench rehab, MH adjustment, and new frame and cover will be completed on MH 8417-01 and MH 9907-166.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/19/2025 | Traffic Control set-up approved between 7AM - 5PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0825-01023
Permit Description: 325003 Site 2 - Install approximately 343 LF of 8" Cured in Place Pipe from MH 8417-01 to MH 9907-166. Bench rehab, MH adjustment, and new frame and cover will be completed on MH 8417-01 and MH 9907-166.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/24/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 11/24/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 11/24/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 11/24/2025 | TRSP - ROW - Final | Passed |