Permit: TR-ROW-0825-01012
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW)
Address:
1709 S CRAYCROFT RD
Address NEW:
1709 S CRAYCROFT RD
Apply Date:
08/14/2025
Applicant:
Andrea Charles
Description:
Trenching through alley for underground electrical conduit installation.
Permit Reviews
Permit Number - TR-ROW-0825-01012
Permit Status: Complete
Permit Description: Trenching through alley for underground electrical conduit installation.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/20/2025 | RIGHT-OF-WAY REVIEW v.2 | 08/20/2025 | APPROVED |
| 08/14/2025 | RIGHT-OF-WAY REVIEW v.1 | 08/15/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0825-01012
Permit Status: Complete
Permit Description: Trenching through alley for underground electrical conduit installation.
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 08/14/2025 | Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvement and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced. |
| 08/15/2025 | Traffic Control set-up approved between 7AM - 5PM |
| 08/20/2025 | Your project work requires that you contact City of Tucson Environmental Services Department (520-791-3171) at least 24 hours prior to closing any street or alley. |
| 08/20/2025 | Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING |
| 08/20/2025 | Private Property Driveways and private property shall NOT be utilized without the owner’s consent. It is the contractor’s responsibility to negotiate use of private property. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0825-01012
Permit Description: Trenching through alley for underground electrical conduit installation.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/17/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | I spoke with Michael over the phone, and he informed me that the trenching across the alleyway had already been completed, and he furnish me with a few pictures. | |
| 09/18/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | Work is complete | |
| 09/18/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | Work is complete | |
| 10/03/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 10/16/2025 | TRSP - ROW - Final | Passed |