Permit: TR-ROW-0825-01002
Permit Details
Apply Date:
08/11/2025
Applicant:
Benjamin Lozano - Border Traffic Safety LLC
Description:
BORDERLAND CONSTRUCTION HAS A HIGH PRIORITY MANHOLE RECONSTRUCTION (MH9852-03), WORK NEEDS TO BE COMPLETE BEFORE AUGUST 25TH SO KE&G CAN PAVE THE AREA PER THE PROP 411 AGREEMENT
Permit Reviews
Permit Number - TR-ROW-0825-01002
Permit Status: Complete
Permit Description: BORDERLAND CONSTRUCTION HAS A HIGH PRIORITY MANHOLE RECONSTRUCTION (MH9852-03), WORK NEEDS TO BE COMPLETE BEFORE AUGUST 25TH SO KE&G CAN PAVE THE AREA PER THE PROP 411 AGREEMENT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/11/2025 | RIGHT-OF-WAY REVIEW v.1 | 08/12/2025 | REQUIRES RESUBMIT |
| 08/13/2025 | RIGHT-OF-WAY REVIEW v.2 | 08/13/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0825-01002
Permit Status: Complete
Permit Description: BORDERLAND CONSTRUCTION HAS A HIGH PRIORITY MANHOLE RECONSTRUCTION (MH9852-03), WORK NEEDS TO BE COMPLETE BEFORE AUGUST 25TH SO KE&G CAN PAVE THE AREA PER THE PROP 411 AGREEMENT
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 08/11/2025 | PRE-CON/PAVEMENT/SIDEWALK |
| 08/11/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 08/13/2025 | Message Board to be placed 5 days in advance of Work Start date. Message text to be outlined on Traffic Control Plan. |
| 08/13/2025 | Traffic Control set-up approved between 7AM - 5PM |
| 08/14/2025 | Emergency- inspections |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0825-01002
Permit Description: BORDERLAND CONSTRUCTION HAS A HIGH PRIORITY MANHOLE RECONSTRUCTION (MH9852-03), WORK NEEDS TO BE COMPLETE BEFORE AUGUST 25TH SO KE&G CAN PAVE THE AREA PER THE PROP 411 AGREEMENT
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/18/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 08/15/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 09/04/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 09/04/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 09/04/2025 | TRSP - ROW - Final | Passed |