Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TR-ROW-0825-00985
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW)
Address:
8725 E GIACHERY PL
Address NEW:
8725 E GIACHERY PL
Apply Date:
08/04/2025
Applicant:
Desert Barricade / Eric Horne
Description:
Demo and Repour of 2 Uplifted Sidewalk Panels.
Permit Reviews
Permit Number - TR-ROW-0825-00985
Permit Status: Complete
Permit Description: Demo and Repour of 2 Uplifted Sidewalk Panels.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/06/2026 | RIGHT-OF-WAY REVIEW v.2 | 01/06/2026 | APPROVED |
| 08/04/2025 | RIGHT-OF-WAY REVIEW v.1 | 08/06/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0825-00985
Permit Status: Complete
Permit Description: Demo and Repour of 2 Uplifted Sidewalk Panels.
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 08/05/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 08/05/2025 | SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. REPLACE/REPAIR SIDEWALKS PANELS PER PAG STANDARD DETAIL 200/206 |
| 08/06/2025 | The following extended traffic control set-up times were approved: |
| 08/06/2025 | Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206. PEDESTRIAN DETOUR ROUTE TO BE MAINTAINED ON SAME SIDE OF RIGHT OF WAY AS EXISTING SIDEWALK CLOSURE. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 08/06/2025 | Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING |
| 08/06/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0825-00985
Permit Description: Demo and Repour of 2 Uplifted Sidewalk Panels.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/08/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | I spoke with Michael Dorn over the phone to meet the pre-activity requirements. He told me that he would begin work immediately and would be done within one day. It is a 2 panel repair job | |
| 01/22/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | Work is being done within a controlled traffic zone by Boarderlands. | |
| 01/22/2026 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed | Site is ready for concrete | |
| 01/26/2026 | TRSP - ROW - Final | Passed | Work on this permit is complete | |
| 01/26/2026 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | Passed | Work is complete |