Permit: TR-ROW-0825-00983
Permit Details
Apply Date:
08/04/2025
Applicant:
Description:
325001 Site 1 - Install approximately 179 LF of 8" Cured in Place Pipe from MH 9027-02 to MH 9027-01. Bench rehabs, MH adjustments, and new frame and covers will be completed on MH's 9027-02 and 9027-01.
Permit Reviews
Permit Number - TR-ROW-0825-00983
Permit Status: Complete
Permit Description: 325001 Site 1 - Install approximately 179 LF of 8" Cured in Place Pipe from MH 9027-02 to MH 9027-01. Bench rehabs, MH adjustments, and new frame and covers will be completed on MH's 9027-02 and 9027-01.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/05/2025 | RIGHT-OF-WAY REVIEW v.2 | 08/06/2025 | APPROVED |
| 08/04/2025 | RIGHT-OF-WAY REVIEW v.1 | 08/04/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0825-00983
Permit Status: Complete
Permit Description: 325001 Site 1 - Install approximately 179 LF of 8" Cured in Place Pipe from MH 9027-02 to MH 9027-01. Bench rehabs, MH adjustments, and new frame and covers will be completed on MH's 9027-02 and 9027-01.
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 08/04/2025 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
| 08/04/2025 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0825-00983
Permit Description: 325001 Site 1 - Install approximately 179 LF of 8" Cured in Place Pipe from MH 9027-02 to MH 9027-01. Bench rehabs, MH adjustments, and new frame and covers will be completed on MH's 9027-02 and 9027-01.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/08/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 08/18/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 11/05/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 11/05/2025 | TRSP - ROW - Final | Passed |