Permit: TR-ROW-0824-00959
Permit Details
Apply Date:
08/19/2024
Applicant:
Erica Goldston
Description:
Hunter will be removing and replacing VCP to PVC, Bench rehabs, Installing new Manholes, CIPP Lining.
Permit Reviews
Permit Number - TR-ROW-0824-00959
Permit Status: Complete
Permit Description: Hunter will be removing and replacing VCP to PVC, Bench rehabs, Installing new Manholes, CIPP Lining.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/19/2024 | RIGHT-OF-WAY REVIEW REVISION v.1 | 09/20/2024 | APPROVED |
| 09/13/2024 | RIGHT-OF-WAY REVIEW REVISION v.1 | 09/16/2024 | APPROVED |
| 08/29/2024 | RIGHT-OF-WAY REVIEW REVISION v.1 | 09/11/2024 | APPROVED |
| 08/19/2024 | RIGHT-OF-WAY REVIEW v.1 | 08/20/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0824-00959
Permit Status: Complete
Permit Description: Hunter will be removing and replacing VCP to PVC, Bench rehabs, Installing new Manholes, CIPP Lining.
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 08/20/2024 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
| 08/20/2024 | Traffic control set-up approved between 9AM - 3:30PM |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-ROW-0824-00959
Permite Description: Hunter will be removing and replacing VCP to PVC, Bench rehabs, Installing new Manholes, CIPP Lining.
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/03/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | N/A | Re-inspection required | |
| 10/07/2024 | TRSP - ROW - Barricade - Setup/Routine | N/A | Partial Pass | |
| 10/16/2024 | TRSP - ROW - Barricade Takedown | N/A | Re-inspection required | |
| 11/26/2024 | TRSP - ROW - Final | N/A | Re-inspection required |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0824-00959
Permit Description: Hunter will be removing and replacing VCP to PVC, Bench rehabs, Installing new Manholes, CIPP Lining.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/09/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 10/16/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 05/02/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 05/02/2025 | TRSP - ROW - Final | Passed |