Permit: TR-ROW-0726-00859
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW)
Address:
6401 S TUCSON BL
Address NEW:
6401 S TUCSON BL
Apply Date:
07/28/2026
Applicant:
Caitlin Ripley - Southwest Barricades
Description:
Installation of underground conduit for fiber optic cable for new IT connection to DPS from the nearest Pima County IT fiber source.
Permit Reviews
Permit Number - TR-ROW-0726-00859
Permit Status: Inspections
Permit Description: Installation of underground conduit for fiber optic cable for new IT connection to DPS from the nearest Pima County IT fiber source.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/29/2026 | RIGHT-OF-WAY REVIEW v.1 | N/A | REQUIRES RESUBMIT |
| 09/09/2026 | RIGHT-OF-WAY REVIEW v.3 | 09/10/2026 | REQUIRES RESUBMIT |
| 09/11/2026 | RIGHT-OF-WAY REVIEW v.4 | 09/14/2026 | APPROVED |
| 08/19/2026 | RIGHT-OF-WAY REVIEW v.2 | 09/08/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0726-00859
Permit Status: Inspections
Permit Description: Installation of underground conduit for fiber optic cable for new IT connection to DPS from the nearest Pima County IT fiber source.
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 08/20/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 08/20/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 08/20/2026 | PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 09/11/2026 | The following extended traffic control set-up times were approved: |
| 09/11/2026 | Traffic Control set-up approved between 7AM - 5PM |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-ROW-0726-00859
Permit Description: Installation of underground conduit for fiber optic cable for new IT connection to DPS from the nearest Pima County IT fiber source.
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/21/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 09/21/2026 | Required: Start Work Notice - Notify your DTM Inspector of your work start date. Notification only; you will be contacted if a Pre-Activity Meeting is needed. | Passed |