Permit: TR-ROW-0726-00841
Permit Details
Status:
Needs Resubmittal
Type:
Right-of-Way (ROW)
Address:
5726 E 19TH ST
Address NEW:
5726 E 19TH ST
Apply Date:
07/22/2026
Applicant:
Benjamin Lozano - Border Traffic Safety LLC
Description:
Potholing for San Fernando future phases 3,4 & 5. This potholing is for design purposes.
Permit Reviews
Permit Number - TR-ROW-0726-00841
Permit Status: Needs resubmittal
Permit Description: Potholing for San Fernando future phases 3,4 & 5. This potholing is for design purposes.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/28/2026 | RIGHT-OF-WAY REVIEW v.2 | 08/17/2026 | REQUIRES RESUBMIT |
| 07/22/2026 | RIGHT-OF-WAY REVIEW v.1 | N/A | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0726-00841
Permit Status: Needs resubmittal
Permit Description: Potholing for San Fernando future phases 3,4 & 5. This potholing is for design purposes.
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 07/28/2026 | Traffic Control set-up approved between 7AM - 5PM |
| 07/28/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 07/28/2026 | UNDER A PAVEMENT MORATORIUM, ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES. |
| 07/28/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 07/28/2026 | PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 08/17/2026 | Potholing operations shall be conducted in a manner that maintains public safety and minimizes impacts to traffic. All excavations shall be properly protected, backfilled, and restored upon completion. The permittee shall be responsible for repairing any settlement or pavement failure resulting from potholing activities at no cost to the City. |
| 08/17/2026 | The contractor shall not block driveways or restrict resident access without prior notification and shall coordinate directly with affected property owners as necessary |