Permit: TR-ROW-0726-00827
Permit Details
Apply Date:
07/20/2026
Applicant:
Adam Bishop
Description:
Installation of new sidewalk and driveway apron within the current city CIP project limits. 08/31/2026 - Work is Not related to the CIP, however, this is bound by the 5th Av boundaries. Work will be done be same contractor, Hunter Contracting, however, this will be done as a private development. Work will the completed within the same confines of the traffic control.
Permit Reviews
Permit Number - TR-ROW-0726-00827
Permit Status: Complete
Permit Description: Installation of new sidewalk and driveway apron within the current city CIP project limits.
08/31/2026 - Work is Not related to the CIP, however, this is bound by the 5th Av boundaries. Work will be done be same contractor, Hunter Contracting, however, this will be done as a private development. Work will the completed within the same confines of the traffic control.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/29/2026 | RIGHT-OF-WAY REVIEW v.2 | N/A | REQUIRES RESUBMIT |
| 09/02/2026 | RIGHT-OF-WAY REVIEW v.3 | 09/02/2026 | APPROVED |
| 07/21/2026 | RIGHT-OF-WAY REVIEW v.1 | N/A | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0726-00827
Permit Status: Complete
Permit Description: Installation of new sidewalk and driveway apron within the current city CIP project limits.
08/31/2026 - Work is Not related to the CIP, however, this is bound by the 5th Av boundaries. Work will be done be same contractor, Hunter Contracting, however, this will be done as a private development. Work will the completed within the same confines of the traffic control.
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 07/29/2026 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
| 07/29/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 07/29/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 07/29/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 07/29/2026 | PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 07/29/2026 | PER MUTCD PROPER ADVANCED WARNING SIGNS AHEAD ARE REQUIRED. PEDESTRAIN ACCESS MUST BE PROVIDED AND MAINTAINED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. REPLACE/REPAIR SIDEWALKS PANELS PER PAG STANDARD DETAIL 200/206 |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0726-00827
Permit Description: Installation of new sidewalk and driveway apron within the current city CIP project limits.
08/31/2026 - Work is Not related to the CIP, however, this is bound by the 5th Av boundaries. Work will be done be same contractor, Hunter Contracting, however, this will be done as a private development. Work will the completed within the same confines of the traffic control.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/08/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed |