Permit: TR-ROW-0726-00821
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW)
Address:
4105 S EVERGREEN AV
Address NEW:
4105 S EVERGREEN AV
Apply Date:
07/16/2026
Applicant:
Description:
5 rocklined basins and 1 mulched basin planted with Trees and shrubs.
Permit Reviews
Permit Number - TR-ROW-0726-00821
Permit Status: Inspections
Permit Description: 5 rocklined basins and 1 mulched basin planted with Trees and shrubs.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/16/2026 | RIGHT-OF-WAY REVIEW v.1 | 08/05/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0726-00821
Permit Status: Inspections
Permit Description: 5 rocklined basins and 1 mulched basin planted with Trees and shrubs.
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 07/20/2026 | **Pre-Activity Meeting w/Inspections **Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 – 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 07/20/2026 | Traffic Control set-up approved between 7AM - 5PM |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-ROW-0726-00821
Permit Description: 5 rocklined basins and 1 mulched basin planted with Trees and shrubs.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/10/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | phone call with Rebecca, job will be mobilizing this week for an anticipated three week duration |