The scope of work includes furnishing and installing approximately 1325 linear feet of 8-inch PVC, 2900 linear feet of 6-inch PVC, 225 linear feet of 4-inch PVC, 100 linear feet of 6-inch DIP, gate valves, cut & cap with DVA, fire hydrants, concrete-asbestos pipe removal, water meter relocations and service connections. Pavement replacement as indicated on the drawings
Permit Reviews
Permit Number - TR-ROW-0725-00907
Permit Status: Complete
Permit Description: The scope of work includes furnishing and installing approximately 1325 linear feet of 8-inch PVC, 2900 linear feet of 6-inch PVC, 225 linear feet of 4-inch PVC, 100 linear feet of 6-inch DIP, gate valves, cut & cap with DVA, fire hydrants, concrete-asbestos pipe removal, water meter relocations and service connections. Pavement replacement as indicated on the drawings
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/14/2025 | RIGHT-OF-WAY REVIEW v.1 | 07/16/2025 | REQUIRES RESUBMIT |
| 07/21/2025 | RIGHT-OF-WAY REVIEW v.3 | 07/23/2025 | APPROVED |
| 07/17/2025 | RIGHT-OF-WAY REVIEW v.2 | 07/17/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0725-00907
Permit Status: Complete
Permit Description: The scope of work includes furnishing and installing approximately 1325 linear feet of 8-inch PVC, 2900 linear feet of 6-inch PVC, 225 linear feet of 4-inch PVC, 100 linear feet of 6-inch DIP, gate valves, cut & cap with DVA, fire hydrants, concrete-asbestos pipe removal, water meter relocations and service connections. Pavement replacement as indicated on the drawings
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 07/15/2025 | PRE-CON/PAVEMENT/SIDEWALK |
| 07/15/2025 | Traffic Control set-up approved between 7AM - 5PM |
| 07/15/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 07/15/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-ROW-0725-00907
Permite Description: The scope of work includes furnishing and installing approximately 1325 linear feet of 8-inch PVC, 2900 linear feet of 6-inch PVC, 225 linear feet of 4-inch PVC, 100 linear feet of 6-inch DIP, gate valves, cut & cap with DVA, fire hydrants, concrete-asbestos pipe removal, water meter relocations and service connections. Pavement replacement as indicated on the drawings
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/06/2025 | TRSP - ROW - Backfill - Placement/Compaction | N/A | Re-inspection required |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0725-00907
Permit Description: The scope of work includes furnishing and installing approximately 1325 linear feet of 8-inch PVC, 2900 linear feet of 6-inch PVC, 225 linear feet of 4-inch PVC, 100 linear feet of 6-inch DIP, gate valves, cut & cap with DVA, fire hydrants, concrete-asbestos pipe removal, water meter relocations and service connections. Pavement replacement as indicated on the drawings
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/25/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 08/27/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 09/05/2025 | TRSP - ROW - Bituminous Treatment | Passed | ||
| 10/22/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 11/19/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 01/16/2026 | TRSP - ROW - Final | Passed |