Permit: TR-ROW-0724-00833
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW)
Address:
750 E IRVINGTON RD BLDG 1
Address NEW:
750 E IRVINGTON RD BLDG 1
Apply Date:
07/19/2024
Applicant:
Blake Olofson
Description:
ROW Permit for air-vacuum excavation of 1 utility pothole approximately 12"x12" in size for the design phase of the HSIP HAWK Crossing Projects Package 2 project. Consultant Project Manager is Andy McGovern andrew.mcgovern@psomas.com. City PM is Blake Olofson.
Permit Reviews
Permit Number - TR-ROW-0724-00833
Permit Status: Inspections
Permit Description: ROW Permit for air-vacuum excavation of 1 utility pothole approximately 12"x12" in size for the design phase of the HSIP HAWK Crossing Projects Package 2 project. Consultant Project Manager is Andy McGovern andrew.mcgovern@psomas.com. City PM is Blake Olofson.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/19/2024 | RIGHT-OF-WAY REVIEW v.2 | 08/19/2024 | REQUIRES RESUBMIT |
| 07/23/2024 | RIGHT-OF-WAY REVIEW v.1 | 07/25/2024 | REQUIRES RESUBMIT |
| 09/25/2024 | RIGHT-OF-WAY REVIEW v.3 | 09/30/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0724-00833
Permit Status: Inspections
Permit Description: ROW Permit for air-vacuum excavation of 1 utility pothole approximately 12"x12" in size for the design phase of the HSIP HAWK Crossing Projects Package 2 project. Consultant Project Manager is Andy McGovern andrew.mcgovern@psomas.com. City PM is Blake Olofson.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/25/2024 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-ROW-0724-00833
Permit Description: ROW Permit for air-vacuum excavation of 1 utility pothole approximately 12"x12" in size for the design phase of the HSIP HAWK Crossing Projects Package 2 project. Consultant Project Manager is Andy McGovern andrew.mcgovern@psomas.com. City PM is Blake Olofson.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/28/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed |