Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TR-ROW-0724-00770
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW)
Address:
261 W FORT LOWELL RD
Address NEW:
261 W FORT LOWELL RD
Apply Date:
07/09/2024
Applicant:
Dan Padilla
Description:
ROW Permit for air-vacuum excavation of 3 utility potholes approximately 12"x12" in size for the design phase of the HSIP HAWK Crossing Projects Package 2 project. Consultant Project Manager is Andy McGovern andrew.mcgovern@psomas.com
Permit Reviews
Permit Number - TR-ROW-0724-00770
Permit Status: Complete
Permit Description: ROW Permit for air-vacuum excavation of 3 utility potholes approximately 12"x12" in size for the design phase of the HSIP HAWK Crossing Projects Package 2 project. Consultant Project Manager is Andy McGovern andrew.mcgovern@psomas.com
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/10/2024 | RIGHT-OF-WAY REVIEW v.1 | 07/26/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0724-00770
Permit Status: Complete
Permit Description: ROW Permit for air-vacuum excavation of 3 utility potholes approximately 12"x12" in size for the design phase of the HSIP HAWK Crossing Projects Package 2 project. Consultant Project Manager is Andy McGovern andrew.mcgovern@psomas.com
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 07/10/2024 | PRE-CON/PAVEMENT/SIDEWALK |
| 07/10/2024 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0724-00770
Permit Description: ROW Permit for air-vacuum excavation of 3 utility potholes approximately 12"x12" in size for the design phase of the HSIP HAWK Crossing Projects Package 2 project. Consultant Project Manager is Andy McGovern andrew.mcgovern@psomas.com
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/27/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 10/03/2024 | TRSP - ROW - Paving - Subgrade/removal/placement | Passed | ||
| 10/03/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 10/03/2024 | TRSP - ROW - Final | Passed |