Permit: TR-ROW-0626-00723
Permit Details
Status:
Issued
Type:
Right-of-Way (ROW)
Address:
6163 S MIDVALE PARK RD
Address NEW:
6163 S MIDVALE PARK RD
Apply Date:
06/17/2026
Applicant:
Alexis Otero-Morales
Description:
18" L X 18" Wide 18" D in asphalt to raise water vale. Valve is the red circle on site plan.*** 11/02/2026 - Request for 30 Day Renewal as of 11/06/2026
Permit Reviews
Permit Number - TR-ROW-0626-00723
Permit Status: Issued
Permit Description: 18" L X 18" Wide 18" D in asphalt to raise water vale. Valve is the red circle on site plan.***
11/02/2026 - Request for 30 Day Renewal as of 11/06/2026
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/17/2026 | RIGHT-OF-WAY REVIEW v.1 | 06/26/2026 | REQUIRES RESUBMIT |
| 09/21/2026 | RIGHT-OF-WAY REVIEW v.2 | 10/05/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0626-00723
Permit Status: Issued
Permit Description: 18" L X 18" Wide 18" D in asphalt to raise water vale. Valve is the red circle on site plan.***
11/02/2026 - Request for 30 Day Renewal as of 11/06/2026
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 06/18/2026 | |
| 06/18/2026 | Traffic control set-up approved between 9AM - 3:30PM |
Outstanding Inspections
Permit Status: Issued
Permit Number: TR-ROW-0626-00723
Permite Description: 18" L X 18" Wide 18" D in asphalt to raise water vale. Valve is the red circle on site plan.***
11/02/2026 - Request for 30 Day Renewal as of 11/06/2026
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/13/2026 | TRSP - ROW - Barricade - Setup/Routine | N/A | Partial Pass | |
| TRSP - ROW - Backfill - Placement/Compaction | N/A | Requested | ||
| TRSP - ROW - Final | N/A | Requested |
Completed Inspections
Permit Status: Issued
Permit Number: TR-ROW-0626-00723
Permit Description: 18" L X 18" Wide 18" D in asphalt to raise water vale. Valve is the red circle on site plan.***
11/02/2026 - Request for 30 Day Renewal as of 11/06/2026
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/09/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed |