Permit: TR-ROW-0626-00710
Permit Details
Apply Date:
06/12/2026
Applicant:
Caitlin Ripley - Southwest Barricades
Description:
This permit request is for authorization to perform sewer excavation and repair work extending beyond the private property line and into the public right-of-way, including the sidewalk and street directly in front of the residence. Work will involve saw-cutting pavement, excavating to access the existing sewer line, completing necessary repairs, and restoring all disturbed areas to City of Tucson standards. Traffic control, barricades, and safety measures will be implemented in accordance with City requirements to ensure public safety and maintain proper ROW conditions throughout the duration of the project.
Permit Reviews
Permit Number - TR-ROW-0626-00710
Permit Status: Complete
Permit Description: This permit request is for authorization to perform sewer excavation and repair work extending beyond the private property line and into the public right-of-way, including the sidewalk and street directly in front of the residence. Work will involve saw-cutting pavement, excavating to access the existing sewer line, completing necessary repairs, and restoring all disturbed areas to City of Tucson standards. Traffic control, barricades, and safety measures will be implemented in accordance with City requirements to ensure public safety and maintain proper ROW conditions throughout the duration of the project.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/12/2026 | RIGHT-OF-WAY REVIEW v.1 | N/A | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0626-00710
Permit Status: Complete
Permit Description: This permit request is for authorization to perform sewer excavation and repair work extending beyond the private property line and into the public right-of-way, including the sidewalk and street directly in front of the residence. Work will involve saw-cutting pavement, excavating to access the existing sewer line, completing necessary repairs, and restoring all disturbed areas to City of Tucson standards. Traffic control, barricades, and safety measures will be implemented in accordance with City requirements to ensure public safety and maintain proper ROW conditions throughout the duration of the project.
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 06/15/2026 | Monsoon Season started June 15th, 2026 to September 30th,2026 - Debre and Physical blockages prohibiting Water Flow to be removed. All trenches will be required to be back filled at the end of each working day, and may not be opened if prediction of rain is above 0% within 3 days of work prior to post. |
| 06/15/2026 | Traffic Control set-up approved between 7AM - 5PM |
| 06/15/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 06/15/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 06/15/2026 | PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 06/15/2026 | PER MUTCD PROPER ADVANCED WARNING SIGNS AHEAD ARE REQUIRED. PEDESTRAIN ACCESS MUST BE PROVIDED AND MAINTAINED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0626-00710
Permit Description: This permit request is for authorization to perform sewer excavation and repair work extending beyond the private property line and into the public right-of-way, including the sidewalk and street directly in front of the residence. Work will involve saw-cutting pavement, excavating to access the existing sewer line, completing necessary repairs, and restoring all disturbed areas to City of Tucson standards. Traffic control, barricades, and safety measures will be implemented in accordance with City requirements to ensure public safety and maintain proper ROW conditions throughout the duration of the project.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/16/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | onsite meeting with Martin, discussed backfill materials, traffic control signs, and roadway restoration | |
| 06/17/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | Lane closure with tapering and advanced warnings are in place. Sidewalk needs to be closed with Route to other side of the street. | |
| 06/18/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | bedding sand in place around pipe, AB backfill for roadway | |
| 06/23/2026 | TRSP - ROW - Final | Passed | pavement restored using non-moratorium T top method, sidewalk panel replaced with new expansion joints, traffic control devices removed from site, approved |