Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
In Review
Type:
Right-of-Way (ROW)
Address:
855 W PRINCE RD
Address NEW:
855 W PRINCE RD
Apply Date:
06/10/2026
Applicant:
angel islas
Description:
ROW Permit for Barricade placement, potholing, and waterline installation in one traffic lane on Fairview Road south of Prince.

Permit Reviews

Permit Number - TR-ROW-0626-00701
Permit Status: In review
Permit Description: ROW Permit for Barricade placement, potholing, and waterline installation in one traffic lane on Fairview Road south of Prince.
Start Date Submittal Complete Date Status  
06/11/2026 RIGHT-OF-WAY REVIEW v.1 N/A IN REVIEW Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0626-00701
Permit Status: In review
Permit Description: ROW Permit for Barricade placement, potholing, and waterline installation in one traffic lane on Fairview Road south of Prince.
Total Outstanding Activity Conditions - 5
Date Name
06/11/2026 Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.
06/11/2026 PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 – 42 Refer to COT 2015 Addition to the MUTCD section 14
06/11/2026 Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online.
06/11/2026 Traffic control set-up approved between 9AM - 3:30PM
06/11/2026 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.