Permit: TR-ROW-0624-00739
Permit Details
Apply Date:
06/27/2024
Applicant:
DANNY COCOA
Description:
Install by trench and directional bore (1) 2" conduit fiber optic pathway at 36" deep for 1,470ft and 6ft from curve line in row per drawing 30 days for excavation and resurfacing.
Permit Reviews
Permit Number - TR-ROW-0624-00739
Permit Status: Complete
Permit Description: Install by trench and directional bore (1) 2" conduit fiber optic pathway at 36" deep for 1,470ft and 6ft from curve line in row per drawing 30 days for excavation and resurfacing.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/18/2024 | RIGHT-OF-WAY REVIEW v.4 | 08/19/2024 | APPROVED |
06/27/2024 | RIGHT-OF-WAY REVIEW v.1 | 07/03/2024 | REQUIRES RESUBMIT |
08/09/2024 | RIGHT-OF-WAY REVIEW v.2 | 08/13/2024 | REQUIRES RESUBMIT |
08/14/2024 | RIGHT-OF-WAY REVIEW v.3 | 08/15/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0624-00739
Permit Status: Complete
Permit Description: Install by trench and directional bore (1) 2" conduit fiber optic pathway at 36" deep for 1,470ft and 6ft from curve line in row per drawing 30 days for excavation and resurfacing.
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
06/28/2024 | Traffic control set-up approved between 9AM - 3:30PM |
06/28/2024 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
06/28/2024 | Pavement Patch type Shall Be in conformance to the current edition of the City of Tucson Public Utility Administrative Manual. |
06/28/2024 | PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 |
06/28/2024 | Prop 411 project work area, Contact Nick Germanos at Nick.Germanos@tucsonaz.gov or James Degrood at James.degrood@tucsonaz.gov prior to start of work |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0624-00739
Permit Description: Install by trench and directional bore (1) 2" conduit fiber optic pathway at 36" deep for 1,470ft and 6ft from curve line in row per drawing 30 days for excavation and resurfacing.
Total Completed Inspections - 6
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/21/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | work and boring done in row to be inspected by Chris. contractor will make contact once they are ready to start next week. trenching and boring in the private end will be visually inspected by Chris. per Jesus v cot it is ok to go into the islands for trenching. row will watch and inspect all work in row. no surface treatment is required due to existing roadway conditions. patches will be T top. | |
09/19/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | job complete, no elements on site | |
09/19/2024 | TRSP - ROW - Paving - Subgrade/removal/placement | Passed | job completed with boring, no asphalt impacted | |
09/19/2024 | TRSP - ROW - Barricade Takedown | Passed | all barricades and traffic control removed | |
09/19/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | vaults placed and backfill accepted | |
09/19/2024 | TRSP - ROW - Final/Close-Out | Passed | All work completed, worksite, cleaned, and clear of traffic control, job closed |