Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address NEW:
7441 E CALLE ARTURO
Apply Date:
06/11/2024
Applicant:
Cameron Bonner
Description:
323069 Site 2 - PCRWRD Asset Address is 300 S. Prudence Rd. CIPP LINING AND DISCHARGE PIPE. ON PRUDENCE FROM CALLE ARTURO TO CALLE MADERO Install Approximately 405 LF of 8" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench rehab's and new concrete collars will be completed on MH's 2447-07 and MH 2447-06 per PCRWRD standard detail 212. Traffic Control will be in place 24 hours to protect the bypass required for this location. Working hours will be 7am to 4pm.

Permit Reviews

Permit Number - TR-ROW-0624-00678
Permit Status: Complete
Permit Description: 323069 Site 2 - PCRWRD Asset Address is 300 S. Prudence Rd. CIPP LINING AND DISCHARGE PIPE. ON PRUDENCE FROM CALLE ARTURO TO CALLE MADERO Install Approximately 405 LF of 8" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench rehab's and new concrete collars will be completed on MH's 2447-07 and MH 2447-06 per PCRWRD standard detail 212. Traffic Control will be in place 24 hours to protect the bypass required for this location. Working hours will be 7am to 4pm.
Start Date Submittal Complete Date Status  
06/11/2024 RIGHT-OF-WAY REVIEW v.1 06/25/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0624-00678
Permit Status: Complete
Permit Description: 323069 Site 2 - PCRWRD Asset Address is 300 S. Prudence Rd. CIPP LINING AND DISCHARGE PIPE. ON PRUDENCE FROM CALLE ARTURO TO CALLE MADERO Install Approximately 405 LF of 8" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench rehab's and new concrete collars will be completed on MH's 2447-07 and MH 2447-06 per PCRWRD standard detail 212. Traffic Control will be in place 24 hours to protect the bypass required for this location. Working hours will be 7am to 4pm.
Total Outstanding Activity Conditions - 2
Date Name
06/11/2024 PRE-CON/PAVEMENT/SIDEWALK
06/11/2024 Traffic control set-up approved between 9AM - 3:30PM

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0624-00678
Permit Description: 323069 Site 2 - PCRWRD Asset Address is 300 S. Prudence Rd. CIPP LINING AND DISCHARGE PIPE. ON PRUDENCE FROM CALLE ARTURO TO CALLE MADERO Install Approximately 405 LF of 8" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench rehab's and new concrete collars will be completed on MH's 2447-07 and MH 2447-06 per PCRWRD standard detail 212. Traffic Control will be in place 24 hours to protect the bypass required for this location. Working hours will be 7am to 4pm.
Total Completed Inspections - 5
Date Description Inspector Results Comments
07/08/2024 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
09/26/2024 TRSP - ROW - Barricade - Setup/Routine Passed
09/26/2024 TRSP - ROW - Barricade Takedown Passed
09/26/2024 TRSP - ROW - Backfill - Placement/Compaction Passed
09/26/2024 TRSP - ROW - Notice of Completion Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
323069 - SITE 2 FMP MAP (300 S. PRUDENCE RD) - 1_V1.PDF DOCUMENTS VIEW
PAGE 2 - DB 69509 - T323069 - 300 S. PRUDENCE_V1.PDF DOCUMENTS VIEW