2 tie-ins at electric poles for TEP electric/joint trench along Camino Santiago-No traffic control needed work is in the shoulder of roadway-North tie-in (151' in dirt) & South tie-in (21' in dirt) Work zone will be barricaded
Permit Reviews
Permit Number - TR-ROW-0526-00584
Permit Status: Complete
Permit Description: 2 tie-ins at electric poles for TEP electric/joint trench along Camino Santiago-No traffic control needed work is in the shoulder of roadway-North tie-in (151' in dirt) & South tie-in (21' in dirt)
Work zone will be barricaded
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/13/2026 | RIGHT-OF-WAY REVIEW v.1 | 05/21/2026 | REQUIRES RESUBMIT |
| 06/01/2026 | RIGHT-OF-WAY REVIEW v.2 | N/A | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0526-00584
Permit Status: Complete
Permit Description: 2 tie-ins at electric poles for TEP electric/joint trench along Camino Santiago-No traffic control needed work is in the shoulder of roadway-North tie-in (151' in dirt) & South tie-in (21' in dirt)
Work zone will be barricaded
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 05/20/2026 | **Pre-Activity Meeting w/Inspections **Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 – 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 05/20/2026 | Bus stop in the area, contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 at least 48-business hours prior to start of work for coordination. |
| 05/20/2026 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0526-00584
Permit Description: 2 tie-ins at electric poles for TEP electric/joint trench along Camino Santiago-No traffic control needed work is in the shoulder of roadway-North tie-in (151' in dirt) & South tie-in (21' in dirt)
Work zone will be barricaded
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/03/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 08/07/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | all areas of the right away for the St. Mary's side of his project have been completed the remainder of the word design private properties development for the PIA | |
| 09/02/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | all areas of the right away for the St. Mary's side of his project have been completed the remainder of the word design private properties development for the PIA | |
| 09/02/2026 | TRSP - ROW - Final | Passed | all areas of the right away for the St. Mary's side of his project have been completed the remainder of the word design private properties development for the PIA |