Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address:
1050 E 8TH ST
Address NEW:
1050 E 8TH ST
Apply Date:
05/08/2026
Applicant:
Description:
Manhole bench rehab

Permit Reviews

Permit Number - TR-ROW-0526-00561
Permit Status: Complete
Permit Description: Manhole bench rehab
Start Date Submittal Complete Date Status  
05/11/2026 RIGHT-OF-WAY REVIEW v.1 05/14/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0526-00561
Permit Status: Complete
Permit Description: Manhole bench rehab
Total Outstanding Activity Conditions - 2
Date Name
05/13/2026 **Pre-Activity Meeting w/Inspections **Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 – 42 Refer to COT 2015 Addition to the MUTCD section 14
05/13/2026 Traffic Control set-up approved between 7AM - 5PM

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0526-00561
Permit Description: Manhole bench rehab
Total Completed Inspections - 4
Date Description Inspector Results Comments
06/24/2026 TRSP - ROW - Barricade - Setup/Routine Passed
06/24/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
06/24/2026 TRSP - ROW - Backfill - Placement/Compaction Passed
06/24/2026 TRSP - ROW - Final Passed