Permit: TR-ROW-0526-00528
Permit Details
Apply Date:
05/04/2026
Applicant:
Katie Ledy
Description:
Requesting permit to install new vertical curb, asphalt patching, concrete aprons, & concrete sidewalk for new building.
Permit Reviews
Permit Number - TR-ROW-0526-00528
Permit Status: Complete
Permit Description: Requesting permit to install new vertical curb, asphalt patching, concrete aprons, & concrete sidewalk for new building.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/05/2026 | RIGHT-OF-WAY REVIEW v.1 | N/A | REQUIRES RESUBMIT |
| 05/18/2026 | RIGHT-OF-WAY REVIEW v.2 | 05/21/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0526-00528
Permit Status: Complete
Permit Description: Requesting permit to install new vertical curb, asphalt patching, concrete aprons, & concrete sidewalk for new building.
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 05/05/2026 | Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvement and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced. |
| 05/05/2026 | City of Tucson Right of Way Only |
| 05/05/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 05/05/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 05/05/2026 | PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 05/20/2026 | Right of Way Impact extending to Half or more of ROW will require separate and additional Traffic Control plans |
| 05/20/2026 | Traffic Control set-up approved between 7AM - 5PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0526-00528
Permit Description: Requesting permit to install new vertical curb, asphalt patching, concrete aprons, & concrete sidewalk for new building.
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/27/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | Existing documents and pictures checked and verified the drawings to make sure everything is correct in the right away and it is that they're following their drawings per the letter | |
| 06/02/2026 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed | Pree poor post poor photos uploaded waiting for the concrete tickets and the rest of verifications to be emailed to me for compaction | |
| 06/24/2026 | TRSP - ROW - Final | Passed | all sidewalk repairs and new sidewalk and driveway. Aprons and asphalt has been complete completed. | |
| 06/24/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | All work complete | |
| 06/24/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | All work complete inspection not needed | |
| 06/24/2026 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | Passed |