Permit: TR-ROW-0526-00524
Permit Details
Apply Date:
05/01/2026
Applicant:
Caitlin Southwest
Description:
Installation of a cathodic protection system for the SWGAS natural gas steel pipeline. Critical to preventative corrosion mitigation to the natural gas steel pipeline.
Permit Reviews
Permit Number - TR-ROW-0526-00524
Permit Status: Complete
Permit Description: Installation of a cathodic protection system for the SWGAS natural gas steel pipeline. Critical to preventative corrosion mitigation to the natural gas steel pipeline.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/01/2026 | RIGHT-OF-WAY REVIEW v.1 | 05/11/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0526-00524
Permit Status: Complete
Permit Description: Installation of a cathodic protection system for the SWGAS natural gas steel pipeline. Critical to preventative corrosion mitigation to the natural gas steel pipeline.
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 05/07/2026 | **Pre-Activity Meeting w/Inspections **Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 – 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 05/07/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 05/11/2026 | - Lane closures shall only be permitted during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four (24) hour lane closures are not permitted unless specifically approved by the City. Traffic Control Devices shall not be stored in the bike lane or sidewalk. |
| 05/11/2026 | Continuous ADA-compliant pedestrian access shall be maintained at all times. If sidewalks are closed, an approved temporary pedestrian access route shall be provided in accordance with the Manual on Uniform Traffic Control Devices. |
| 05/11/2026 | Excavation - All excavations must be securely plated or backfilled at the end of each workday and during any period when the site is unattended. Plating shall be traffic-rated, flush with the surrounding surface, and properly secured to prevent movement and to maintain public safety |
| 05/11/2026 | Pavement Restoration - The contractor shall restore all disturbed pavement in accordance with the City of Tucson Standard Specifications for Public Improvements and applicable standard details. All pavement patches shall match the existing pavement section and surface condition. The contractor shall maintain all temporary patches in a safe and drivable condition until permanent restoration is completed. Any settlement, cracking, or pavement failure within the patched area shall be repaired by the contractor at no cost to the City for the duration of the warranty period |
| 05/11/2026 | Works shall be completed by July 6th, 2024 in time for the start of the voter approved project starting in the area. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0526-00524
Permit Description: Installation of a cathodic protection system for the SWGAS natural gas steel pipeline. Critical to preventative corrosion mitigation to the natural gas steel pipeline.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/19/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 06/01/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 06/17/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | backfill with the cathartic protection for this well has been completed. They will be getting a new permit when they gotta do more work for the power for the cathartic well | |
| 06/22/2026 | TRSP - ROW - Final | Passed | all work completed for this phase of the permit |