Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address NEW:
818 E SPEEDWAY BL
Apply Date:
05/27/2025
Applicant:
ANGEL MORALES
Description:
Trench 650’ L X 3’W X 4’D to in asphalt to install new water line. Install 6 new service lines 4’D X 30’L X 2’W. *812 E SPEEDWAY (ADDRESS NOT IN SYSTEM)*** Permit update 7/22/2025: Renewal request for 60 days.

Permit Reviews

Permit Number - TR-ROW-0525-00733
Permit Status: Complete
Permit Description: Trench 650’ L X 3’W X 4’D to in asphalt to install new water line. Install 6 new service lines 4’D X 30’L X 2’W. *812 E SPEEDWAY (ADDRESS NOT IN SYSTEM)*** Permit update 7/22/2025: Renewal request for 60 days.
Start Date Submittal Complete Date Status  
05/28/2025 RIGHT-OF-WAY REVIEW v.1 06/04/2025 REQUIRES RESUBMIT Review Details
07/31/2025 RIGHT-OF-WAY REVIEW REVISION v.1 07/31/2025 APPROVED Review Details
06/12/2025 RIGHT-OF-WAY REVIEW REVISION v.2 06/12/2025 APPROVED Review Details
06/11/2025 RIGHT-OF-WAY REVIEW REVISION v.1 06/12/2025 REQUIRES RESUBMIT Review Details
06/05/2025 RIGHT-OF-WAY REVIEW v.2 06/09/2025 APPROVED Review Details
06/10/2025 RIGHT-OF-WAY REVIEW REVISION v.1 06/10/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0525-00733
Permit Status: Complete
Permit Description: Trench 650’ L X 3’W X 4’D to in asphalt to install new water line. Install 6 new service lines 4’D X 30’L X 2’W. *812 E SPEEDWAY (ADDRESS NOT IN SYSTEM)*** Permit update 7/22/2025: Renewal request for 60 days.
Total Outstanding Activity Conditions - 10
Date Name
05/28/2025 BUS STOP/ ROUTE
05/28/2025 PRE-CON/PAVEMENT/SIDEWALK
05/28/2025 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
06/09/2025 The following extended traffic control set-up times were approved: 24 hr
06/09/2025 Pavement restoration
06/09/2025 Travel lanes will need to be reopened prior to University of Arizona's fall semester. Academic year will begin on August 26, 2025
06/10/2025 TNE
06/12/2025 Contact DTM Public Information Office 48 hours prior to road closure and after it has been reopened.
06/12/2025 Contact Fire Department 48 hours prior to road closure and after it has been reopened.
06/12/2025 Traffic control measures are subject to change based on public feedback and safety evaluations.

Outstanding Inspections

Permit Status: Complete
Permit Number: TR-ROW-0525-00733
Permite Description: Trench 650’ L X 3’W X 4’D to in asphalt to install new water line. Install 6 new service lines 4’D X 30’L X 2’W. *812 E SPEEDWAY (ADDRESS NOT IN SYSTEM)*** Permit update 7/22/2025: Renewal request for 60 days.
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
TRSP - ROW - Final N/A Requested
TRSP – PIA – Underground Utility/Joint Trench N/A Scheduled

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0525-00733
Permit Description: Trench 650’ L X 3’W X 4’D to in asphalt to install new water line. Install 6 new service lines 4’D X 30’L X 2’W. *812 E SPEEDWAY (ADDRESS NOT IN SYSTEM)*** Permit update 7/22/2025: Renewal request for 60 days.
Total Completed Inspections - 4
Date Description Inspector Results Comments
06/10/2025 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
07/11/2025 TRSP - ROW - Barricade - Setup/Routine Passed
07/11/2025 TRSP - ROW - Barricade Takedown Passed Off roadway by 6:00 am
07/17/2025 TRSP - ROW - Backfill - Placement/Compaction Passed

Scheduled Inspections

Scheduled Inspections - TR-ROW-0525-00733
Status: Complete
Description: Trench 650’ L X 3’W X 4’D to in asphalt to install new water line. Install 6 new service lines 4’D X 30’L X 2’W. *812 E SPEEDWAY (ADDRESS NOT IN SYSTEM)*** Permit update 7/22/2025: Renewal request for 60 days.
Scheduled Date Description Entered By Entered Date
11/29/2025 TRSP – PIA – Underground Utility/Joint Trench Scheduled
For information about today’s scheduled inspections please refer to the PDSD Daily Inspections Dashboards (Desktop) PDSD Daily Inspections Dashboards (Mobile) .