Permit: TR-ROW-0525-00729
Permit Details
Apply Date:
05/27/2025
Applicant:
CAITLIN RIPLEY - SOUTHWEST BARRICADES
Description:
New HCS tie into sewer main 9/5/2025- 30 day renewal as of 9/7/25. New expiration date is 10/7/25
Permit Reviews
Permit Number - TR-ROW-0525-00729
Permit Status: Complete
Permit Description: New HCS tie into sewer main
9/5/2025- 30 day renewal as of 9/7/25. New expiration date is 10/7/25
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/25/2025 | RIGHT-OF-WAY REVIEW v.2 | 07/28/2025 | APPROVED |
| 05/27/2025 | RIGHT-OF-WAY REVIEW v.1 | 06/27/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0525-00729
Permit Status: Complete
Permit Description: New HCS tie into sewer main
9/5/2025- 30 day renewal as of 9/7/25. New expiration date is 10/7/25
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 05/27/2025 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
| 05/27/2025 | Traffic Control set-up approved between 7AM - 5PM |
| 05/28/2025 | Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 05/28/2025 | UNDER A PAVEMENT MORATORIUM, ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0525-00729
Permit Description: New HCS tie into sewer main
9/5/2025- 30 day renewal as of 9/7/25. New expiration date is 10/7/25
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/12/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 08/26/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 09/10/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 09/11/2025 | TRSP - ROW - Final | Passed |