Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address NEW:
3902 E SPEEDWAY BL
Apply Date:
05/20/2025
Applicant:
Bryan Guinee
Description:
The contractor will be installing cameras onto light poles for the Tucson Police Department. Shadow Truck less than an hour per location. 60 day Permit.

Permit Reviews

Permit Number - TR-ROW-0525-00698
Permit Status: Complete
Permit Description: The contractor will be installing cameras onto light poles for the Tucson Police Department. Shadow Truck less than an hour per location. 60 day Permit.
Start Date Submittal Complete Date Status  
05/28/2025 RIGHT-OF-WAY REVIEW v.2 05/28/2025 APPROVED Review Details
05/20/2025 RIGHT-OF-WAY REVIEW v.1 05/22/2025 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0525-00698
Permit Status: Complete
Permit Description: The contractor will be installing cameras onto light poles for the Tucson Police Department. Shadow Truck less than an hour per location. 60 day Permit.
Total Outstanding Activity Conditions - 4
Date Name
05/20/2025 BUS STOP IN AREA, CONTACT SUN TRAN DISPTCH AT 520.206.8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION.
05/20/2025 Traffic control set-up approved between 9AM - 3:30PM
05/20/2025 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
05/28/2025 Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0525-00698
Permit Description: The contractor will be installing cameras onto light poles for the Tucson Police Department. Shadow Truck less than an hour per location. 60 day Permit.
Total Completed Inspections - 2
Date Description Inspector Results Comments
07/28/2025 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
07/28/2025 TRSP - ROW - Final Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
7. MAP SPEEDWAY - ALVERNON WAY_V1.PDF DOCUMENTS VIEW
7. TCP_NEXT SPEEDWAY - ALVERNON_V2.PDF DOCUMENTS VIEW