Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Withdrawn
Type:
Right-of-Way (ROW)
Address:
3925 N 1ST AV
Address NEW:
3925 N 1ST AV
Apply Date:
05/14/2025
Applicant:
Ash Smith
Description:
(2 of 3) We will be performing SEVEN (7) geotechnical borings within the roadway of N 1st Ave from approximately 200ft south of the intersection of Roger Rd and N 1st Ave to approximately 525ft north of the intersection of N 1st Ave and Fort Lowell Rd. Asphalt coring will be conducted prior to drilling of soil borings. Cores will be obtained using an electric coring rig and will be approximately 10 inches in diameter. The soil borings will be advanced through the 10 inch asphalt core hole with 7 or 8 inch hollow stem auger to depths of approximately 5 feet below the ground surface The borings will be backfilled with auger cuttings mixed with concrete (with concrete comprising between 20 to 50% of the soil-cement backfill). The exposed asphalt concrete at each boring location will be cleaned, wire-brushed, and patched with QPR brand asphalt cold path. (We understand the restoration of boring locations in the existing roadway as described above will be acceptable by the City of Tucson.) If groundwater is encountered during drilling, the boring will be backfilled with cement grout to the state minimum of the upper 20 feet, unless otherwise within the threshold distance of a WQARF, CERCLA, VRP, LUST, or DOD site, the boring(s) will be backfilled with cement grout to the full depth of the boring. See site plan for details on locations of planned boreholes and traffic control plans for anticipated one-lane closures along N 1st Ave. We do not anticipate performing any work within signalized intersections. Requesting no restrictions on work times. 135 to 150ft bridge borings will be performed as night work. Work performed for HDR Engineering for the City of Tucson, Contract No. 230193-01. THIS IS A CITY OF TUCSON PROJECT. Permit is needed by next week to stay on schedule. Please call Louis Braun 952.457.4619 05/20/2025 **WITHDRAW PERMIT AS OF 05/20/2025 DUPLICATE PERMIT**

Permit Reviews

Permit Number - TR-ROW-0525-00665
Permit Status: Withdrawn
Permit Description: (2 of 3) We will be performing SEVEN (7) geotechnical borings within the roadway of N 1st Ave from approximately 200ft south of the intersection of Roger Rd and N 1st Ave to approximately 525ft north of the intersection of N 1st Ave and Fort Lowell Rd. Asphalt coring will be conducted prior to drilling of soil borings. Cores will be obtained using an electric coring rig and will be approximately 10 inches in diameter. The soil borings will be advanced through the 10 inch asphalt core hole with 7 or 8 inch hollow stem auger to depths of approximately 5 feet below the ground surface The borings will be backfilled with auger cuttings mixed with concrete (with concrete comprising between 20 to 50% of the soil-cement backfill). The exposed asphalt concrete at each boring location will be cleaned, wire-brushed, and patched with QPR brand asphalt cold path. (We understand the restoration of boring locations in the existing roadway as described above will be acceptable by the City of Tucson.) If groundwater is encountered during drilling, the boring will be backfilled with cement grout to the state minimum of the upper 20 feet, unless otherwise within the threshold distance of a WQARF, CERCLA, VRP, LUST, or DOD site, the boring(s) will be backfilled with cement grout to the full depth of the boring. See site plan for details on locations of planned boreholes and traffic control plans for anticipated one-lane closures along N 1st Ave. We do not anticipate performing any work within signalized intersections. Requesting no restrictions on work times. 135 to 150ft bridge borings will be performed as night work. Work performed for HDR Engineering for the City of Tucson, Contract No. 230193-01. THIS IS A CITY OF TUCSON PROJECT. Permit is needed by next week to stay on schedule. Please call Louis Braun 952.457.4619 05/20/2025 **WITHDRAW PERMIT AS OF 05/20/2025 DUPLICATE PERMIT**
Start Date Submittal Complete Date Status  
05/15/2025 RIGHT-OF-WAY REVIEW v.1 05/19/2025 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0525-00665
Permit Status: Withdrawn
Permit Description: (2 of 3) We will be performing SEVEN (7) geotechnical borings within the roadway of N 1st Ave from approximately 200ft south of the intersection of Roger Rd and N 1st Ave to approximately 525ft north of the intersection of N 1st Ave and Fort Lowell Rd. Asphalt coring will be conducted prior to drilling of soil borings. Cores will be obtained using an electric coring rig and will be approximately 10 inches in diameter. The soil borings will be advanced through the 10 inch asphalt core hole with 7 or 8 inch hollow stem auger to depths of approximately 5 feet below the ground surface The borings will be backfilled with auger cuttings mixed with concrete (with concrete comprising between 20 to 50% of the soil-cement backfill). The exposed asphalt concrete at each boring location will be cleaned, wire-brushed, and patched with QPR brand asphalt cold path. (We understand the restoration of boring locations in the existing roadway as described above will be acceptable by the City of Tucson.) If groundwater is encountered during drilling, the boring will be backfilled with cement grout to the state minimum of the upper 20 feet, unless otherwise within the threshold distance of a WQARF, CERCLA, VRP, LUST, or DOD site, the boring(s) will be backfilled with cement grout to the full depth of the boring. See site plan for details on locations of planned boreholes and traffic control plans for anticipated one-lane closures along N 1st Ave. We do not anticipate performing any work within signalized intersections. Requesting no restrictions on work times. 135 to 150ft bridge borings will be performed as night work. Work performed for HDR Engineering for the City of Tucson, Contract No. 230193-01. THIS IS A CITY OF TUCSON PROJECT. Permit is needed by next week to stay on schedule. Please call Louis Braun 952.457.4619 05/20/2025 **WITHDRAW PERMIT AS OF 05/20/2025 DUPLICATE PERMIT**
Total Outstanding Activity Conditions - 4
Date Name
05/16/2025 BUS STOP/ ROUTE
05/16/2025 PRE-CON/PAVEMENT/SIDEWALK
05/16/2025 Traffic control set-up approved between 9AM - 3:30PM
05/16/2025 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.