Permit: TR-ROW-0525-00629
Permit Details
Apply Date:
05/07/2025
Applicant:
ANGEL MORALES
Description:
Jo 124058- CIPP, Concrete work around MH, Concrete work inside manhole
Permit Reviews
Permit Number - TR-ROW-0525-00629
Permit Status: Complete
Permit Description: Jo 124058- CIPP, Concrete work around MH, Concrete work inside manhole
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/07/2025 | RIGHT-OF-WAY REVIEW v.1 | 05/09/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0525-00629
Permit Status: Complete
Permit Description: Jo 124058- CIPP, Concrete work around MH, Concrete work inside manhole
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 05/08/2025 | PAVEMENT MORATORIUM: |
| 05/08/2025 | PRE-CON/PAVEMENT/SIDEWALK |
| 05/08/2025 | Traffic Control set-up approved between 7AM - 5PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0525-00629
Permit Description: Jo 124058- CIPP, Concrete work around MH, Concrete work inside manhole
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/23/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 06/23/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 06/23/2025 | TRSP - ROW - Final | Passed |