Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TR-ROW-0525-00624
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW)
Address:
3400 S LA CHOLLA BL
Address NEW:
3400 S LA CHOLLA BL
Apply Date:
05/07/2025
Applicant:
Desert Barricades LLC
Description:
Starting March 20, 2025-June 30, 2025 due to paving the parking lot of the project, the contractor and subcontractors will need to park on the street with their materials being in storage containers on the side of the road as well.
Permit Reviews
Permit Number - TR-ROW-0525-00624
Permit Status: Complete
Permit Description: Starting March 20, 2025-June 30, 2025 due to paving the parking lot of the project, the contractor and subcontractors will need to park on the street with their materials being in storage containers on the side of the road as well.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/07/2025 | RIGHT-OF-WAY REVIEW v.1 | 05/07/2025 | REQUIRES RESUBMIT |
| 05/08/2025 | RIGHT-OF-WAY REVIEW v.2 | 05/09/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0525-00624
Permit Status: Complete
Permit Description: Starting March 20, 2025-June 30, 2025 due to paving the parking lot of the project, the contractor and subcontractors will need to park on the street with their materials being in storage containers on the side of the road as well.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/08/2025 | Traffic Control set-up approved between 7AM - 5PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0525-00624
Permit Description: Starting March 20, 2025-June 30, 2025 due to paving the parking lot of the project, the contractor and subcontractors will need to park on the street with their materials being in storage containers on the side of the road as well.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/13/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 05/15/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 05/15/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 09/12/2025 | TRSP - ROW - Final | Passed |