Permit: TR-ROW-0525-00607
Permit Details
Status:
Issued
Type:
Right-of-Way (ROW)
Address:
6163 S MIDVALE PARK RD
Address NEW:
6163 S MIDVALE PARK RD
Apply Date:
05/05/2025
Applicant:
ANGEL MORALES
Description:
Trench 113’ L X 4’D X 2’W install 8” water line. Remove and replace 16’ of vertical Curb.*** 06/16/2025-REQUEST FOR 60 DAY EXTENSION AS OF 06/18/2025
Permit Reviews
Permit Number - TR-ROW-0525-00607
Permit Status: Issued
Permit Description: Trench 113’ L X 4’D X 2’W install 8” water line. Remove and replace 16’ of vertical Curb.***
06/16/2025-REQUEST FOR 60 DAY EXTENSION AS OF 06/18/2025
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/27/2025 | RIGHT-OF-WAY REVIEW REVISION v.1 | 07/01/2025 | APPROVED |
| 05/13/2025 | RIGHT-OF-WAY REVIEW v.2 | 05/13/2025 | APPROVED |
| 05/06/2025 | RIGHT-OF-WAY REVIEW v.1 | 05/07/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0525-00607
Permit Status: Issued
Permit Description: Trench 113’ L X 4’D X 2’W install 8” water line. Remove and replace 16’ of vertical Curb.***
06/16/2025-REQUEST FOR 60 DAY EXTENSION AS OF 06/18/2025
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 05/06/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 05/06/2025 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
| 05/13/2025 | PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRATIVE MANUAL. |
| 05/13/2025 | PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS IF LOCATED WITHIN 660' OF CLOSURE. PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED IF NO ADA RAMPS ACCESSABLE. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2 |
| 05/13/2025 | Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 06/30/2025 | Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions |
Outstanding Inspections
Permit Status: Issued
Permit Number: TR-ROW-0525-00607
Permite Description: Trench 113’ L X 4’D X 2’W install 8” water line. Remove and replace 16’ of vertical Curb.***
06/16/2025-REQUEST FOR 60 DAY EXTENSION AS OF 06/18/2025
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/22/2025 | TRSP - ROW - Paving - Subgrade/removal/placement | N/A | Partial Pass | |
| 08/22/2025 | TRSP - ROW - Final | N/A | Re-inspection required |
Completed Inspections
Permit Status: Issued
Permit Number: TR-ROW-0525-00607
Permit Description: Trench 113’ L X 4’D X 2’W install 8” water line. Remove and replace 16’ of vertical Curb.***
06/16/2025-REQUEST FOR 60 DAY EXTENSION AS OF 06/18/2025
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/13/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 07/30/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed |