Permit Details

Status:
Denied
Type:
Right-of-Way (ROW)
Address:
160 E ALAMEDA ST
Address NEW:
160 E ALAMEDA ST
Apply Date:
05/23/2024
Applicant:
Miguel Gonzalez
Description:
Maintance Permit: possible dig ups, for conduit crushed pipes. At existing Zayo HH locations an extra HH will be place. Begin at STA 0+00, by means pull through, pull fiber along existing Zayo conduits, with 288F micro cable. Place new Zayo HH at STA 1+10. Pull along Alameda St. to E Tools Ave. for approx. 1029' Place Zayo HH at STA 9+70. Resume pulling cable to STA 20+60. Place HH at STA 20+70. Resume pulling cable along existing ducts to STA 30+70. Place Zayo HH at STA 30+80, resume pulling cable to STA 44+90. Place Zayo HH at STA 45+00. Was originally TR-ROW-0524-00603

Permit Reviews

Permit Number - TR-ROW-0524-00622
Permit Status: Denied
Permit Description: Maintance Permit: possible dig ups, for conduit crushed pipes. At existing Zayo HH locations an extra HH will be place. Begin at STA 0+00, by means pull through, pull fiber along existing Zayo conduits, with 288F micro cable. Place new Zayo HH at STA 1+10. Pull along Alameda St. to E Tools Ave. for approx. 1029' Place Zayo HH at STA 9+70. Resume pulling cable to STA 20+60. Place HH at STA 20+70. Resume pulling cable along existing ducts to STA 30+70. Place Zayo HH at STA 30+80, resume pulling cable to STA 44+90. Place Zayo HH at STA 45+00. Was originally TR-ROW-0524-00603
Start Date Submittal Complete Date Status  
05/23/2024 RIGHT-OF-WAY REVIEW v.1 05/24/2024 REQUIRES RESUBMIT Review Details