Permit: TR-ROW-0426-00461
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW)
Address:
4950 E SPEEDWAY BL
Address NEW:
4950 E SPEEDWAY BL
Apply Date:
04/22/2026
Applicant:
ANGEL MORALES
Description:
CIPP, sewer line point repair, and replace existing concrete collars 06/11/2026 - Request for 30 Day Renewal as of 06/13/2026
Permit Reviews
Permit Number - TR-ROW-0426-00461
Permit Status: Complete
Permit Description: CIPP, sewer line point repair, and replace existing concrete collars
06/11/2026 - Request for 30 Day Renewal as of 06/13/2026
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/22/2026 | RIGHT-OF-WAY REVIEW v.1 | 05/11/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0426-00461
Permit Status: Complete
Permit Description: CIPP, sewer line point repair, and replace existing concrete collars
06/11/2026 - Request for 30 Day Renewal as of 06/13/2026
Total Outstanding Activity Conditions - 9
| Date | Name |
|---|---|
| 04/22/2026 | Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 04/22/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 04/22/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 04/22/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 04/24/2026 | - The contractor shall restore all disturbed pavement in accordance with the City of Tucson Standard Specifications for Public Improvements and applicable standard details. All pavement patches shall match the existing pavement section and surface condition. The contractor shall maintain all temporary patches in a safe and drivable condition until permanent restoration is completed. Any settlement, cracking, or pavement failure within the patched area shall be repaired by the contractor at no cost to the City for the duration of the warranty period |
| 04/24/2026 | All excavations must be securely plated or backfilled at the end of each workday and during any period when the site is unattended. Plating shall be traffic-rated, flush with the surrounding surface, and properly secured to prevent movement and to maintain public safety |
| 04/24/2026 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION WITH jose.garcia@tucsonaz.gov.. Due to the presence of a bus stop in the area, the contractor is required to contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 no less than 48 business hours before beginning work to coordinate impacts. |
| 04/24/2026 | Lane closures shall only be permitted during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four (24) hour lane closures are not permitted unless specifically approved by the City. Traffic Control Devices shall not be stored in the bike lane or sidewalk |
| 04/24/2026 | The contractor shall always maintain safe and continuous access to all adjacent businesses during construction. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0426-00461
Permit Description: CIPP, sewer line point repair, and replace existing concrete collars
06/11/2026 - Request for 30 Day Renewal as of 06/13/2026
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/19/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 06/01/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 06/11/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 06/11/2026 | TRSP - ROW - Final | Passed |