Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address NEW:
110 E PENNINGTON ST
Apply Date:
04/15/2026
Applicant:
Benjamin Lozano - Border Traffic Safety LLC
Description:
perform required excavation at SE corner of Scott and Pennington to reroute existing underground infrastructure. This is to facilitate fiber optic cable installation for Pima County. 06/05/2026 - Request for 30 Day Renewal as of 06/12/2026

Permit Reviews

Permit Number - TR-ROW-0426-00437
Permit Status: Complete
Permit Description: perform required excavation at SE corner of Scott and Pennington to reroute existing underground infrastructure. This is to facilitate fiber optic cable installation for Pima County. 06/05/2026 - Request for 30 Day Renewal as of 06/12/2026
Start Date Submittal Complete Date Status  
05/04/2026 RIGHT-OF-WAY REVIEW v.2 05/08/2026 APPROVED Review Details
04/15/2026 RIGHT-OF-WAY REVIEW v.1 04/24/2026 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0426-00437
Permit Status: Complete
Permit Description: perform required excavation at SE corner of Scott and Pennington to reroute existing underground infrastructure. This is to facilitate fiber optic cable installation for Pima County. 06/05/2026 - Request for 30 Day Renewal as of 06/12/2026
Total Outstanding Activity Conditions - 7
Date Name
04/17/2026 This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to the Historic Preservation Office, City of Tucson, PO BOX 27210, Tucson AZ 85726...***Please contact Historic Preservation Office at PDSDHistoric@tucsonaz.gov.
04/17/2026 ROW Permit is only allowed for work within City of Tucson Right of Way.
04/17/2026 Traffic control set-up approved between 9AM - 3:30PM
04/17/2026 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
04/17/2026 Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online.
04/17/2026 Driveways and private property shall NOT be utilized without the owner’s consent. It is the contractor’s responsibility to negotiate use of private property.
04/17/2026 PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0426-00437
Permit Description: perform required excavation at SE corner of Scott and Pennington to reroute existing underground infrastructure. This is to facilitate fiber optic cable installation for Pima County. 06/05/2026 - Request for 30 Day Renewal as of 06/12/2026
Total Completed Inspections - 4
Date Description Inspector Results Comments
05/18/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
06/29/2026 TRSP - ROW - Barricade - Setup/Routine Passed
06/29/2026 TRSP - ROW - Backfill - Placement/Compaction Passed
06/29/2026 TRSP - ROW - Final Passed