Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address NEW:
7424 E SPEEDWAY BL
Apply Date:
04/02/2026
Applicant:
ANGEL MORALES
Description:
CIPP and replace existing concrete collars 05/13/26- Renew for 30 days as of 05/15/26 new expiration date is 08/13/26.

Permit Reviews

Permit Number - TR-ROW-0426-00390
Permit Status: Complete
Permit Description: CIPP and replace existing concrete collars 05/13/26- Renew for 30 days as of 05/15/26 new expiration date is 08/13/26.
Start Date Submittal Complete Date Status  
04/02/2026 RIGHT-OF-WAY REVIEW v.1 04/08/2026 REQUIRES RESUBMIT Review Details
04/10/2026 RIGHT-OF-WAY REVIEW v.2 N/A APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0426-00390
Permit Status: Complete
Permit Description: CIPP and replace existing concrete collars 05/13/26- Renew for 30 days as of 05/15/26 new expiration date is 08/13/26.
Total Outstanding Activity Conditions - 5
Date Name
04/02/2026 Traffic control set-up approved between 9AM - 3:30PM
04/13/2026 The following extended traffic control set-up times were approved: TC Closure Only
04/13/2026 Due to the presence of a bus stop in the area, the contractor is required to contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 no less than 48 business hours before beginning work to coordinate impacts.
04/13/2026 MESSAGE BOARDS REQUIRED - 5 days in advance of Work.
04/13/2026 Pre-Activity Meeting w/Inspections Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0426-00390
Permit Description: CIPP and replace existing concrete collars 05/13/26- Renew for 30 days as of 05/15/26 new expiration date is 08/13/26.
Total Completed Inspections - 4
Date Description Inspector Results Comments
04/20/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
06/09/2026 TRSP - ROW - Backfill - Placement/Compaction Passed
08/24/2026 TRSP - ROW - Barricade - Setup/Routine Passed
08/24/2026 TRSP - ROW - Final Passed