Permit: TR-ROW-0425-00542
Permit Details
Apply Date:
04/24/2025
Applicant:
Bryan Guinee
Description:
The contractor will be installing cameras onto light poles for the Tucson Police Department. Shadow Truck less than an hour per location. 60-day Permit.
Permit Reviews
Permit Number - TR-ROW-0425-00542
Permit Status: Complete
Permit Description: The contractor will be installing cameras onto light poles for the Tucson Police Department. Shadow Truck less than an hour per location. 60-day Permit.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/24/2025 | RIGHT-OF-WAY REVIEW v.1 | 04/28/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0425-00542
Permit Status: Complete
Permit Description: The contractor will be installing cameras onto light poles for the Tucson Police Department. Shadow Truck less than an hour per location. 60-day Permit.
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 04/25/2025 | BUS STOP IN AREA, CONTACT SUN TRAN DISPTCH AT 520.206.8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
| 04/25/2025 | Approved & Uploaded Temporary Noise Exemption (TNE) will be required prior to Start of Night Work. Within City of Tucson Right of Way |
| 04/25/2025 | PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS IF LOCATED WITHIN 660' OF CLOSURE. PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED IF NO ADA RAMPS ACCESSABLE. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. |
| 04/25/2025 | Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING |
| 04/25/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 04/25/2025 | Work may require track access and meter hooding. Send an email to Sunlink and Park Tucson to advise them of this work. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0425-00542
Permit Description: The contractor will be installing cameras onto light poles for the Tucson Police Department. Shadow Truck less than an hour per location. 60-day Permit.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/30/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 06/30/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 06/30/2025 | TRSP - ROW - Final | Passed |