Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address:
1110 W GLENN ST
Address NEW:
1110 W GLENN ST
Apply Date:
04/18/2025
Applicant:
Andrew Ruiz
Description:
Installing plumbing valve box covers, daytime hard closure 9AM to 3:30PM***

Permit Reviews

Permit Number - TR-ROW-0425-00525
Permit Status: Complete
Permit Description: Installing plumbing valve box covers, daytime hard closure 9AM to 3:30PM***
Start Date Submittal Complete Date Status  
04/18/2025 RIGHT-OF-WAY REVIEW v.1 04/28/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0425-00525
Permit Status: Complete
Permit Description: Installing plumbing valve box covers, daytime hard closure 9AM to 3:30PM***
Total Outstanding Activity Conditions - 4
Date Name
04/21/2025 ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D.
04/21/2025 Traffic control set-up approved between 9AM - 3:30PM
04/28/2025 OTHER ACTIVITIES IN THE AREA, WILL NEED TO COORDINATE TRAFFIC CONTROL SETUP WITH EXISTING SETUP.
04/28/2025 Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0425-00525
Permit Description: Installing plumbing valve box covers, daytime hard closure 9AM to 3:30PM***
Total Completed Inspections - 4
Date Description Inspector Results Comments
06/02/2025 TRSP - ROW - Barricade - Setup/Routine Passed
06/02/2025 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
06/02/2025 TRSP - ROW - Backfill - Placement/Compaction Passed
06/02/2025 TRSP - ROW - Final Passed