Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address NEW:
6936 E SPEEDWAY BL
Apply Date:
04/30/2024
Applicant:
Cameron Bonner
Description:
323066 Sites 2 and 3 - Install Approximately 1010 LF of 10" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench Rehab's and new concrete collars will be completed on MH's 8319-02, 8319-01, 8316-01 per PCRWRD standard detail 211. Update TCP revision 6/4/2024

Permit Reviews

Permit Number - TR-ROW-0424-00500
Permit Status: Complete
Permit Description: 323066 Sites 2 and 3 - Install Approximately 1010 LF of 10" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench Rehab's and new concrete collars will be completed on MH's 8319-02, 8319-01, 8316-01 per PCRWRD standard detail 211. Update TCP revision 6/4/2024
Start Date Submittal Complete Date Status  
04/30/2024 RIGHT-OF-WAY REVIEW v.1 05/02/2024 REQUIRES RESUBMIT Review Details
06/04/2024 RIGHT-OF-WAY REVIEW v.1 06/04/2024 APPROVED Review Details
05/03/2024 RIGHT-OF-WAY REVIEW v.2 05/06/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0424-00500
Permit Status: Complete
Permit Description: 323066 Sites 2 and 3 - Install Approximately 1010 LF of 10" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench Rehab's and new concrete collars will be completed on MH's 8319-02, 8319-01, 8316-01 per PCRWRD standard detail 211. Update TCP revision 6/4/2024
Total Outstanding Activity Conditions - 4
Date Name
04/30/2024 Traffic control set-up approved between 9AM - 3:30PM
04/30/2024 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
04/30/2024 BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION.
06/04/2024 The following extended traffic control set-up times were approved: 24 Hrs

Outstanding Inspections

Permit Status: Complete
Permit Number: TR-ROW-0424-00500
Permite Description: 323066 Sites 2 and 3 - Install Approximately 1010 LF of 10" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench Rehab's and new concrete collars will be completed on MH's 8319-02, 8319-01, 8316-01 per PCRWRD standard detail 211. Update TCP revision 6/4/2024
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
06/11/2024 TRSP - ROW - Barricade - Setup/Routine N/A Re-inspection required

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0424-00500
Permit Description: 323066 Sites 2 and 3 - Install Approximately 1010 LF of 10" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench Rehab's and new concrete collars will be completed on MH's 8319-02, 8319-01, 8316-01 per PCRWRD standard detail 211. Update TCP revision 6/4/2024
Total Completed Inspections - 3
Date Description Inspector Results Comments
06/03/2024 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
06/11/2024 TRSP - ROW - Barricade Takedown Passed
06/11/2024 TRSP - ROW - Final/Close-Out Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
PAGE 1 THRU 3 - 6936 E SPEEDWAY BLVD - EB LLC - 323066 24HR TCP_V1.PDF DOCUMENTS VIEW
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
PAGE 1 THRU 3 - VMS BOARD REV 6936 E SPEEDWAY BLVD - EB LLC - 323066_V2.PDF DOCUMENTS VIEW
323066 - SITES 2 AND 3 FMP MAP (6936 E. SPEEDWAY BLVD.) - 1_V1.PDF DOCUMENTS VIEW